Permit: TC-COM-0423-01064

Parcel: 141186610


Addresses:

10072 E OLD VAIL RD

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/9/24: j.1/1 and h.7/1 not ready to pour
Ok to pour gridline. J.1/ 1.52, 2,2.65, 3 gridline 1/ h, g.81
01/10/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
01/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/12/24: loading dock screen wall okay to pour will verify weep holes with design team
01/16/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/16/24: gridline A/ 8.2 to 6.4 and gridline B/ 2.8 to 4.9 okay to pour concrete
01/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
01/31/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/31/24: gridline G8 from .9 to end of dock wall. Okay to place concrete
Gridline B MAIN ENTRY PILASTERS okay to place concrete
02/01/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/1/24: gridline d.08 /.79
gridline D FRONT OF GARDEN CENTER
gridline A /7.41
Dock leveler pit bottom slab okay to place concrete
02/02/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/2/24: partial pass for rebar cages before placement. Garden center
02/08/2024 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 2/8/24: gridline 0 from D to G8.1 fence foundation needs to be cleared on sides to close to rebar. reset rebar cages clear water from bottom.
02/21/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/21/24: garden center fence post okay to place concrete. Gridline 4.75 to 7.33 20’ out from Gridline C office area bathroom test pour ok to place concrete
02/23/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
02/24/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/24/24: section 4 interior rebar okay to pour for floor concrete
02/27/2024 COT - HCBU - Excavation/Rebar/Zoning  Canceled 2/27/24: canceled per contractor
02/28/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/28/24: garden center plinth gridline 0.79 5 total okay to place concrete
02/29/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/29/24: lumber yard plinths (3) okay to pour concrete
03/11/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/11/24: Spread footings and plinths were inspected by Teracon and passed. Concrete was poured prior to City Inspection, contractor will submit 3rd party report in portal.
03/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Footings for Garden Center Posts; Eight on North and West sides.
03/26/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass South garden center wall at loading dock area. Ok to place concrete.
03/27/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/27/24: garden center footings for low canopy okay to place concrete
04/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/9/24: main entry concrete okay to place
04/11/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/11/24: okay to place concrete for east side of garden center floor
04/17/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/17/24: garden center loading pad
04/24/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/24/24: gridline 11 c.2 to d.2 okay to pour concrete for footings
05/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/7/24: plinths at entry and exit okay to pour concrete.
05/14/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/14/24: okay to place concrete for generator pad south of building
05/22/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/22/24: partial for exterior pad southeast corner of building
05/29/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/29/24: lumber canopy entrance okay to pour concrete
05/31/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/31/24: drive way north east of lumber yard okay to place concrete
06/06/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/5/24: transformer pad and generator pad okay to place concrete
06/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/10/24: tool rental canopy column footings are properly dug, rebar cage is installed and dobies attached on side to keep the 3" clearance from edge of caisson.
06/14/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/15/24: trc canopy slab okay to pour

Contact: Ethan (832)992-9893
08/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Passed
12/01/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/1/23: footing reinforcing in Section 1 per plan.
12/13/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/23. Footing, south side. Gridlines, J .1–0.9 to J.1–10.1. Interior footings. Gridlines 6E, 6F, 6G, 6H, 7E, 7F, 7G, 7H, 8E, 8F, 8G, 8H,
12/15/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/15/23: footing east side exterior j.1-10.1 to b.9-10.1 . Interior footing gridlines 5H, 4H, 3H, 2H, 5G,4G,3G,2G 5F,4F,3F,3F, E5,E4,E3,E2
Okay to place concrete
COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/18/23: footing at north of building grid line B.9 FROM 8.7 through 2.65
12/20/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/20/23: exterior grid line 2 through .9/ B.9 to G.8
footer .9/g.1 not ready
Footer between 2.85/2.65 on j.1 ready to pour (electrical footing)
12/27/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/27/23: gridline b.9 -4.85 and 2.9 pilasters okay to pour
12/28/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready