Inspection Status: Not Ready
Inspection History: COT - HCEL - Electrical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
|
COT - HCEL - Electrical Above Ceiling |
|
Not Ready |
|
| 06/26/2024 |
COT - HCEL - Electrical Above Ceiling |
|
Canceled |
6/26/24: canceled per contractor |
| 07/02/2024 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
ASDS room #136. Learning center #122. Training room #121. Partial pass pending seismic wires on lighting fixtures in each of these rooms. 7/2/2024 |
| 07/03/2024 |
COT - HCEL - Electrical Above Ceiling |
|
Passed |
7/3/24: Restroom hallway, ASDS #136, Training Room #121, and Learning Center #122 have wires properly attached to light fixtures and grid ceiling. Okay to proceed with ceiling tile installation. |