Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
04/11/2023
Applicant:
Corky Poster
Description:
EXISTING BLDG 8, REHAB, 606 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.

Permit Reviews

Permit Number - TC-COM-0423-01032
Permit Status: Issued
Permit Description: EXISTING BLDG 8, REHAB, 606 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Start Date Submittal Complete Date Status  
06/27/2023 COMMERCIAL REVIEW - FULL v.2 07/03/2023 APPROVED Review Details
04/27/2023 COMMERCIAL REVIEW - FULL v.1 05/30/2023 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0423-01032
Permit Status: Issued
Permit Description: EXISTING BLDG 8, REHAB, 606 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Activity Conditions - 11
Date Name
12/20/2024 AIR BALANCING REPORT IS REQUIRED.
12/20/2024 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
12/20/2024 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
12/20/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
12/20/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
12/20/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
12/20/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
12/20/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
12/20/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
12/20/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
12/20/2024 Prior to project being finalized applicant must provide new water easement recordation information

Conditions

Permit Number - TC-COM-0423-01032
Permit Status: Issued
Permit Description: EXISTING BLDG 8, REHAB, 606 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Date Description Comments
06/16/2023 Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512
04/27/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
06/16/2023 NESHAP Permit is required. (Utilized with commercial demolition permits)
12/20/2024 Verify that Permit #P23SD00041 - Milagro on Oracle - Public Sewer is issued and all fees are paid – Waste water receipt
12/20/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0423-01032
Permite Description: EXISTING BLDG 8, REHAB, 606 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
12/06/2024 BULD - Electrical Clearance N/A Not Applicable
12/13/2024 ENGR Engineering Final N/A Partial Pass Okay for TCO Level 4
12/17/2024 COT - FCON - Alarm - Final N/A Partial Pass Fire Alarm is not complete, need report from State Elevator Inspector.
12/17/2024 COT - FCON - Fire - Final N/A Partial Pass Fire Alarm is not complete, need report from State Elevator Inspector. OK for TCO level 4
12/17/2024 COT - LCBU - Building Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0423-01032
Permit Description: EXISTING BLDG 8, REHAB, 606 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Completed Inspections - 12
Date Description Inspector Results Comments
04/29/2024 COT - LCEL - Electrical Above Ceiling Passed All MEP'S approved in building #8. Okay to insulate and drywall. 4/29/2024
04/29/2024 COT - LCEL - Electrical Intermediate Passed All MEP'S approved in building #8. Okay to insulate and drywall. 4/29/2024
04/29/2024 COT - LCEL - Electrical Underground Passed
04/29/2024 COT - LCEL - Grounding/Bonding Passed
04/29/2024 COT - LCBU - Preslab Passed
05/02/2024 COT - BULD - SWG Clearance Passed
10/01/2024 COT - LCEL - Electrical Progress Passed
12/06/2024 COT - LCEL - Electrical Final Passed
12/06/2024 COT - LCME - Mechanical Final Passed
12/13/2024 COT - LCEL - Outdoor Lighting Passed
12/13/2024 COT - LCPL - Plumbing Final Passed
12/17/2024 COT - FCON - Sprinkler - Final Passed

Documents

File Name Document Type  
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW