Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/03/2025 | COT - LCBU - Building Final | Not Ready | ||
| 02/28/2025 | COT - LCBU - Building Final | Re-inspection required | 2-28-25, no access to building 8, see previous notes related to hose bibs being wrapped and required UV protection for all exterior plastic. | |
| 03/05/2025 | COT - LCBU - Building Final | Passed | ||
| 12/06/2024 | COT - LCBU - Building Final | Not Ready | ||
| 12/10/2024 | COT - LCBU - Building Final | Re-inspection required | Adjust door closers and place safety barricades as discussed 12/10/24: 2 20Amp circuits required at kitchen for small appliances, 90 degree fitting required at exterior condensate drain, properly secure mini split at platform, water heater pressure relief shall not terminate more then 6" above finish grade and less then 2X the pipe diameter, water heater enclosure not installed, hose bibs must be insane wrapped for UV Protection, |
|
| 12/13/2024 | COT - LCBU - Building Final | Partial Pass | 12/13/24: OK FOR LEVEL 4 TCO. | |
| 12/17/2024 | COT - LCBU - Building Final | Not Ready |