Permit: TC-COM-0325-00541
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
2717 E CORONA RD UNIT 150
Address NEW:
2717 E CORONA RD UNIT 150
Apply Date:
03/18/2025
Applicant:
Avinash Karnati
Description:
Tenant improvement to an exiting shell building
Permit Reviews
Permit Number - TC-COM-0325-00541
Permit Status: Complete
Permit Description: Tenant improvement to an exiting shell building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/20/2025 | COMMERCIAL REVIEW - FULL v.3 | 05/20/2025 | APPROVED |
| 04/23/2025 | COMMERCIAL REVIEW - FULL v.2 | 05/13/2025 | REQUIRES RESUBMIT |
| 03/20/2025 | COMMERCIAL REVIEW - FULL v.1 | 04/16/2025 | REQUIRES RESUBMIT |
| 09/02/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 09/29/2025 | APPROVED |
| 12/01/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 12/23/2025 | APPROVED |
| 10/29/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 11/18/2025 | APPROVED |
| 01/14/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/21/2026 | APPROVED |
| 05/20/2025 | RESTAMP - COMMERCIAL v.1 | 05/28/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0325-00541
Permit Status: Complete
Permit Description: Tenant improvement to an exiting shell building
| Date | Description | Comments |
|---|---|---|
| 03/20/2025 | UNIT IDENTIFICATION | |
| 03/20/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/20/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 05/20/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 05/20/2025 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0325-00541
Permite Description: Tenant improvement to an exiting shell building
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/25/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 11/25/2025 Frame/Screw Inspection. New vestibule area. All walls approved. Okay to tape and mud. |
| 09/15/2025 | COT - HCPL - Plumbing Progress | N/A | Re-inspection required | 9-15-25: arrived on site at approximately 950am and noted that pour back had already occurred. Therefore, provide a letter to the city for review & approval documenting that pour back at plumbing areas was done per the 2018 IBC and per approved plans. The Letter must be submitted & approved prior to releasing a C of O. |
| 01/15/2026 | COT - HCBU - Building Final | N/A | Re-inspection required | 1-15-26: lower unisex restroom mirror to 40" to the reflective surface, adjust restroom door to 5 pounds, label receptacle at south wall of business side, install bollard to protect water heater-have architect submit a letter to with installation details, water chlorination in progress-unable to check water, install drinking fountain faceplate, seal all penetrations above ceiling at warehouse side, install locking mechanism at restroom door, provide pictures of labeling of junction boxes at warehouse side, and paint exterior roof drain plastic. |
| 01/15/2026 | COT - HCME - Mechanical Final | N/A | Re-inspection required | 1-15-26: lower unisex restroom mirror to 40" to the reflective surface, adjust restroom door to 5 pounds, label receptacle at south wall of business side, install bollard to protect water heater-have architect submit a letter to with installation details, water chlorination in progress-unable to check water, install drinking fountain faceplate, seal all penetrations above ceiling at warehouse side, install locking mechanism at restroom door, provide pictures of labeling of junction boxes at warehouse side, and paint exterior roof drain plastic. |
| 01/15/2026 | COT - HCPL - Plumbing Final | N/A | Re-inspection required | 1-15-26: lower unisex restroom mirror to 40" to the reflective surface, adjust restroom door to 5 pounds, label receptacle at south wall of business side, install bollard to protect water heater-have architect submit a letter to with installation details, water chlorination in progress-unable to check water, install drinking fountain faceplate, seal all penetrations above ceiling at warehouse side, install locking mechanism at restroom door, provide pictures of labeling of junction boxes at warehouse side, and paint exterior roof drain plastic. |
| 01/21/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0325-00541
Permit Description: Tenant improvement to an exiting shell building
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/30/2025 | COT - HCEL - Electrical Intermediate | Passed | Electric in wall per plan, ok to proceed to drywall | |
| 10/30/2025 | COT - HCME - Mechanical Intermediate | Passed | Electric in wall per plan, ok to proceed to drywall | |
| 10/30/2025 | COT - HCPL - Plumbing Intermediate | Passed | Plumbing in wall per plan, ok to proceed to drywall | |
| 12/04/2025 | COT - HCEL - Electrical Above Ceiling | Passed | 12-4-25: electrical above ceiling approved. | |
| 12/04/2025 | COT - HCBU - Building Progress | Passed | 12-4-25: framing for demising wall between suite 140-110 approved. Suite 170-drywall nailing for demising wall at upper portion to decking approved-okay for tape & texture. | |
| 12/04/2025 | COT - HCME - Mechanical Progress | Passed | 12-4-25: approved. | |
| 12/04/2025 | COT - HCEL - Electrical Progress | Passed | 12-4-25: approved. | |
| 01/05/2026 | BULD - Electrical Clearance | Passed | 1-5-26: okay to energize Unit 150-2. ECO clearance issued to TEP. | |
| 01/14/2026 | COT - FCON - Alarm - Final | Passed | ||
| 01/14/2026 | COT - FCON - Fire - Final | Passed | ||
| 01/14/2026 | ENGR Engineering Final | Passed | unit 150 exterior is complete and safe | |
| 01/14/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 01/14/2026 | COT - FCON - Sprinkler - Final | Passed | Approved on 1/5/26 on permit TF-FCP-0925-00713 | |
| 01/15/2026 | COT - HCEL - Electrical Final | Passed | 1-15-26: approved. | |
| 01/14/2026 | COT - HCPL - Plumbing Progress | Passed | 1-14-26: approved. | |
| 01/20/2026 | COT - HCBU - Building Final | Passed | 1-20-26: building final approved. | |
| 01/20/2026 | COT - HCME - Mechanical Final | Passed | 1-20-26: mechanical final approved. | |
| 01/20/2026 | COT - HCPL - Plumbing Final | Passed | 1-20-26: plumbing final approved. |