Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 01/08/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
1-8-26: see previous notes. |
| 01/14/2026 |
COT - HCPL - Plumbing Progress |
|
Passed |
1-14-26: approved. |
| 08/29/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
8/29/25: ROUGH SOIL FOR UNIT 150 PER APPROVED PLANS. WATER TEST PASSED. |
| 09/15/2025 |
COT - HCPL - Plumbing Progress |
|
Re-inspection required |
9-15-25: arrived on site at approximately 950am and noted that pour back had already occurred. Therefore, provide a letter to the city for review & approval documenting that pour back at plumbing areas was done per the 2018 IBC and per approved plans. The Letter must be submitted & approved prior to releasing a C of O. |
| 09/25/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
9-25-25: underground plumbing for Suite 150 verified per plans and under test. Okay to backfill progress areas. |
| 12/04/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
12-4-25: see notes from 9-25-25. Submit a letter to the city for review documenting that pour back after rough soil was done per plans. |