Permit: TC-COM-0125-00160
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
8284 S CAMINO DE CAFE
Address NEW:
8284 S CAMINO DE CAFE
Apply Date:
01/24/2025
Applicant:
Chris Guinter
Description:
A-FAMILY STORAGE LOT 26 - STORAGE BUILDING - White Box
Permit Reviews
Permit Number - TC-COM-0125-00160
Permit Status: Complete
Permit Description: A-FAMILY STORAGE LOT 26 - STORAGE BUILDING - White Box
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/01/2026 | SPECIAL INSPECTION REVIEW v.1 | 10/01/2026 | REQUIRES RESUBMIT |
| 01/31/2025 | COMMERCIAL REVIEW - FULL v.1 | 02/25/2025 | REQUIRES RESUBMIT |
| 10/15/2026 | SPECIAL INSPECTION REVIEW v.2 | 10/16/2026 | APPROVED |
| 10/21/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/21/2026 | APPROVED |
| 08/20/2025 | RESTAMP - COMMERCIAL v.1 | 08/21/2025 | APPROVED |
| 07/31/2025 | COMMERCIAL REVIEW - FULL v.3 | 08/20/2025 | APPROVED |
| 10/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/28/2025 | APPROVED |
| 05/05/2025 | COMMERCIAL REVIEW - FULL v.2 | 06/04/2025 | REQUIRES RESUBMIT |
| 09/24/2025 | ADMINISTRATIVE v.1 | 09/24/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0125-00160
Permit Status: Complete
Permit Description: A-FAMILY STORAGE LOT 26 - STORAGE BUILDING - White Box
| Date | Description | Comments |
|---|---|---|
| 02/24/2025 | SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED. | |
| 01/31/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/24/2025 | SPECIAL INSPECTION FOR POST INSTALLED EPOXY AND EXPANSION AND MECHANICAL ANCHORS IS REQUIRED.-REVIEW INSTALLATION PROCEDURES PER SPECIFIED ICBO REPORT. | |
| 01/31/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 02/24/2025 | SPECIAL INSPECTION OF SOILD IS REQUIRED.INCLUDING EARTH WORK, COMPACTION, GRADING AND FILLING. | |
| 01/31/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 02/24/2025 | SPECIAL INSPECTION FOR STEEL CONSTRUCTION IS REQUIRED. INCLUDING WELDING, THERMAL CUTTING OR HEATING. | |
| 05/27/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0125-00160
Permite Description: A-FAMILY STORAGE LOT 26 - STORAGE BUILDING - White Box
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/20/2025 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
| 11/10/2025 | COT - LCEL - Grounding/Bonding | N/A | Partial Pass | 11-10-25: partial pass for UFER only. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0125-00160
Permit Description: A-FAMILY STORAGE LOT 26 - STORAGE BUILDING - White Box
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/30/2025 | COT - HCPL - Rough Soil | Passed | 10.30.2025 Approved and under test - okay to backfill with shading materials. |
|
| 11/10/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 11-10-25: excavation/reinforcement verified per details on approved plans. Okay to pour concrete. | |
| 11/10/2025 | COT - LCBU - Preslab | Passed | 11-10-25: preslab approved-Okay for concrete placement. | |
| 11/20/2025 | COT - HCPL - Sewer | Passed | ||
| 02/03/2026 | COT - LCPL - Plumbing Intermediate | Passed | Approved. 2/3/2026 | |
| 03/06/2026 | COT - LCME - Mechanical Intermediate | Passed | 3-6-26: mechanical intermediate inspection approved. Okay to continue with construction. | |
| 03/06/2026 | COT - LCEL - Electrical Intermediate | Passed | 3-6-26: electrical intermediate inspection approved. Okay to continue with construction. | |
| 04/21/2026 | COT - LCBU - Framing | Passed | 4-21-26: okay to tape & texture. | |
| 04/30/2026 | BULD - Electrical Clearance | Passed | 4-30-26: okay to energize-ECO clearance issued to TEP. | |
| 09/25/2026 | COT - FCON - Fire - Final | Passed | ||
| 09/25/2026 | TRSP - ROW - Notice of Completion | Passed | building and development package are complete with complete connections to right of way driveway and sidewalk, devices and debris removed from site, approved | |
| 09/28/2026 | COT - LCEL - Outdoor Lighting | Passed | ||
| 09/28/2026 | COT - LCEL - Grounding/Bonding | Passed | ||
| 09/28/2026 | COT - LCEL - Electrical Underground | Passed | ||
| 09/28/2026 | COT - LCEL - Electrical Final | Passed | ||
| 09/28/2026 | COT - LCME - Mechanical Final | Passed | ||
| 09/28/2026 | COT - LCPL - Plumbing Final | Passed | ||
| 09/28/2026 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 10/23/2026 | COT - LCBU - Building Final | Passed | ||
| 10/23/2026 | ENGR Engineering Final | Passed |