Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
01/31/2024
Applicant:
Carlos Navarro
Description:
BLDG A - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas. The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.

Permit Reviews

Permit Number - TC-COM-0124-00215
Permit Status: Issued
Permit Description: BLDG A - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas. The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Start Date Submittal Complete Date Status  
04/09/2024 COMMERCIAL REVIEW - FULL v.3 05/08/2024 REQUIRES RESUBMIT Review Details
02/08/2024 COMMERCIAL REVIEW - FULL v.2 03/18/2024 REQUIRES RESUBMIT Review Details
08/27/2024 RESTAMP - COMMERCIAL v.1 08/29/2024 APPROVED Review Details
02/02/2024 COMMERCIAL REVIEW - FULL v.1 02/02/2024 REQUIRES RESUBMIT Review Details
08/15/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/19/2024 APPROVED Review Details
07/11/2024 RESTAMP - COMMERCIAL v.1 07/16/2024 APPROVED Review Details
04/21/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 04/21/2025 REQUIRES RESUBMIT Review Details
07/11/2024 COMMERCIAL REVIEW - FULL v.5 07/11/2024 APPROVED Review Details
02/03/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/03/2025 APPROVED Review Details
06/25/2024 COMMERCIAL REVIEW - FULL v.4 07/08/2024 REQUIRES RESUBMIT Review Details
04/23/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.3 04/24/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0124-00215
Permit Status: Issued
Permit Description: BLDG A - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas. The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Total Outstanding Activity Conditions - 9
Date Name
07/01/2024 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
07/01/2024 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
07/01/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/01/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
07/01/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
07/01/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
07/01/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/01/2024 Post-Tension Inspection Report is required.
07/01/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Conditions

Permit Number - TC-COM-0124-00215
Permit Status: Issued
Permit Description: BLDG A - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas. The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Date Description Comments
02/02/2024 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
02/02/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
07/11/2024 Prior to Issuance: This project requires issuance of a Development Package (DP) TD-DEV-0124-00025 permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit.
02/02/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/01/2024 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0124-00215
Permite Description: BLDG A - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas. The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Total Outstanding Inspections - 15
Last Inspection Date Description Inspector Results Comments
03/14/2025 COT - HCBU - Framing N/A Partial Pass 3-14-25, Building 1 nailing for decking approved. Okay to continue with construction.
COT - FCON - Fire - Final N/A Not Ready
04/28/2025 COT - HCBU - Roof Nailing N/A Partial Pass 4-28-25, roof nailing for Building A approved. Okay to continue with construction.
05/14/2025 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass 5/14/25: 1st floor exterior clips and sheathing passed, 2nd floor exterior clip and sheathing partial pass. Pending CS16 at shear walls on 2nd floor
12/06/2024 COT - HCBU - Preslab N/A Partial Pass 12/6/24: reinforcement per plan at building slab. Pending breezeways.
07/29/2025 COT - HCPL - Yard Water Line N/A Partial Pass 7/29/25: partial pass for 20' run of water line from meter location to building
09/03/2025 COT - HCME - Mechanical Intermediate N/A Partial Pass 9-3-25: partial pass for MEP's for upstair units on Building 1. Firefoam all chutes and between kitchen exhausts'.
09/03/2025 COT - HCPL - Plumbing Intermediate N/A Partial Pass 9-3-25: partial pass for MEP's for upstair units on Building 1. Firefoam all chutes and between kitchen exhausts'.
09/03/2025 COT - HCEL - Electrical Progress N/A Partial Pass 9-3-25: partial pass for MEP's for upstair units on Building 1. Firefoam all chutes and between kitchen exhausts'.
08/22/2025 COT - HCBU - Building Above Ceiling N/A Partial Pass 8.21.25: Partial intermediate EW3 walls electrical at balcony's, 1st and 2nd floor.
08/22/2025 COT - HCEL - Electrical Intermediate N/A Partial Pass 8.21.25: Partial intermediate EW3 walls electrical at balcony's, 1st and 2nd floor.
09/04/2025 COT - HCME - Mechanical Progress N/A Partial Pass 9-4-25: firefoam penetrations at marked locations. Add blocking /firefoam where called out during the inspection. Firefoam is required at all chutes/and at kitchen exhaust Boca plates throughout both levels. These items must be inspected before closing out MEP's.
11/21/2024 COT - HCBU - Building Progress N/A Not Ready 11/21/24: not ready
10/29/2024 COT - HCPL - Plumbing Progress N/A Partial Pass Underground Rough Plumbing Inspection Bldg. A. Okay to backfill progress areas. Shading required. 10/29/2024
09/09/2025 COT - HCBU - Interior Shear Bracing N/A Partial Pass 9-9-25: Unit's 114, 113, 123, 124 on Building 1 verified per SW9. Okay to continue construction at progress areas.

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0124-00215
Permit Description: BLDG A - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas. The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Total Completed Inspections - 3
Date Description Inspector Results Comments
07/11/2025 COT - HCBU - Preslab Passed 12/6/24: reinforcement per plan at building slab. Pending breezeways.
7/11/25:Breezeway rebar inspection Bldg.A
10/10/2025 COT - BULD - SWG Clearance Passed 10-10-25: Electrical clearance inspection-okay to energize Building 1 unit's 1105, 1106, 1205, 1206, 1107, 1108, 1208, 1207, 1203, 1204, 1201, 1202, 1103, 1104, 1101, 1102, house panel. An email to NNava@ TEP.com for an ECO clearance was issued.
10/17/2025 BULD - Electrical Clearance Passed 10-10-25: Electrical clearance inspection-okay to energize Building 1 unit's 1105, 1106, 1205, 1206, 1107, 1108, 1208, 1207, 1203, 1204, 1201, 1202, 1103, 1104, 1101, 1102, house panel. An email to NNava@ TEP.com for an ECO clearance was issued.

Documents

File Name Document Type  
DDA TRUSS DESIGN AND LAYOUT_V3_V3.PDF DOCUMENTS VIEW
TC-COM-0124-00215 CONCRETE DEFERRED SUBMITTAL LETTER-2025-04-23_V3.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
01 DESERT DOVE BUILDING- COMBINED DISCIPLINES 3RD SUBMITTAL-6175 MIDVALER1_V1.PDF DOCUMENTS VIEW
04 DESERT DOVE APARTMENTS - GEOTECHNICAL REPORT-6175 MIDVALE_V1.PDF DOCUMENTS VIEW
05 DESERT DOVE ENVELOPE COMPLIANCE CERTIFICATE IECC-6175 MIDVALE_V1.PDF DOCUMENTS VIEW
06 DESERT DOVE STRUCTURAL CALCS_REV 6175 MIDVALE_V1.PDF DOCUMENTS VIEW
DESERT DOVE SPECIAL INSPECTION CERTIFICATES-6175 MIDVALE-2024-08-26_V1.PDF DOCUMENTS VIEW
DESERT DOVE SPECIAL INSPECTION CERTIFICATES-2024-08-15_V1.PDF DOCUMENTS VIEW
05 DESERT DOVE ENVELOPE COMPLIANCE CERTIFICATE IECC_V1.PDF DOCUMENTS VIEW
06 DESERT DOVE STRUCTURAL CALCS_REV 1_3-29-24_V2.PDF DOCUMENTS VIEW
CONS-01 DESERT DOVE BUILDING- COMBINED DISCIPLINES 3RD SUBMITTAL_V4.PDF DOCUMENTS VIEW