Permit: TC-COM-0124-00199
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
1770 S CHERRYBELL SV
Address NEW:
1770 S CHERRYBELL SV
Apply Date:
01/30/2024
Applicant:
Description:
This project involves an added 21,900 SF pre-engineered metal building warehouse to an existing Goodwill resale/warehouse building.
Permit Reviews
Permit Number - TC-COM-0124-00199
Permit Status: Issued
Permit Description: This project involves an added 21,900 SF pre-engineered metal building warehouse to an existing Goodwill resale/warehouse building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/03/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/03/2024 | REQUIRES RESUBMIT |
| 07/15/2024 | COMMERCIAL REVIEW - FULL v.3 | 08/15/2024 | APPROVED |
| 01/30/2024 | COMMERCIAL REVIEW - FULL v.1 | 02/28/2024 | REQUIRES RESUBMIT |
| 04/12/2024 | COMMERCIAL REVIEW - FULL v.2 | 06/04/2024 | REQUIRES RESUBMIT |
| 02/28/2025 | COMMERCIAL REVIEW - FULL v.1 | 03/28/2025 | APPROVED |
| 08/15/2024 | RESTAMP - COMMERCIAL v.1 | 08/16/2024 | APPROVED |
| 09/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 09/10/2024 | REQUIRES RESUBMIT |
| 08/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/06/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0124-00199
Permit Status: Issued
Permit Description: This project involves an added 21,900 SF pre-engineered metal building warehouse to an existing Goodwill resale/warehouse building.
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 06/04/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 06/04/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 06/04/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 06/04/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 06/04/2024 | Masonry Inspection Report submittal review is required. |
| 06/04/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
| 09/03/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
Conditions
Permit Number - TC-COM-0124-00199
Permit Status: Issued
Permit Description: This project involves an added 21,900 SF pre-engineered metal building warehouse to an existing Goodwill resale/warehouse building.
| Date | Description | Comments |
|---|---|---|
| 01/30/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/04/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0124-00199
Permite Description: This project involves an added 21,900 SF pre-engineered metal building warehouse to an existing Goodwill resale/warehouse building.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/06/2026 | BULD - Electrical Clearance | N/A | Re-inspection required | Need access to equipment. 1/6/2026 |
| 11/03/2025 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | |
| 11/04/2025 | COT - HCBU - Preslab | N/A | Partial Pass | Total of 9 columns on A line 15-8. Bolts in place per approved plans. Clearances approved around forms. Okay for concrete placement. 11/4/2025 |
| 10/02/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 10-2-25: reinforcement for front dock footings verified per schedule & details on S400. Okay for concrete placement at progress areas. |
| 10/29/2025 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | Ground rods per plan; will see Ufer connection at future point. |
| 06/09/2026 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 6-9-26: 3/4" schedule 40 electrical conduit & grounding at 3 light pole cages approved. Reinforcement/excavation for cages verified by site. |
| 06/23/2026 | COT - HCPL - Rough Soil | N/A | Partial Pass | 6.23.26 Water line running from meter to new building. |
| 07/14/2026 | COT - HCPL - Plumbing Progress | N/A | Canceled | 7-14-26: canceled-not ready. |
| 07/14/2026 | COT - HCME - Mechanical Progress | N/A | Canceled | 7-14-26: canceled-not ready. |
| 07/14/2026 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 7-14-26: partial pass for phase 1 dock loading/warehouse electrical intermediate. Label all junction boxes and disconnects, verify that 3/4" rigid electrical conduit is supported at 10' maximum intervals and 12' for 1" conduit. |
| 07/28/2026 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 7-28-26: Phase 1 dock loading warehouse water line test near 150 psi-Install a pressure reducing valve. Copper line above ceiling properly supported. Set gas pressure gauge to 15 psi and reschedule when ready. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0124-00199
Permit Description: This project involves an added 21,900 SF pre-engineered metal building warehouse to an existing Goodwill resale/warehouse building.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2025 | COT - HCBU - Framing | Passed | Ok to insulate and Sheetrock bathroom wall; OK to insulate and sheet rock East donation area wall (approximately 85 feet). | |
| 07/14/2025 | COT - HCBU - Building Progress | Passed | Ok to sheet rock progress areas. | |
| 01/09/2026 | BULD - Electrical Clearance | Passed | New switch gear and SES equipment. OK to set meter and energize new service. | |
| 05/29/2026 | COT - HCEL - Electrical Underground | Passed | Passed |