Inspection History Details
Inspection Status: Canceled
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2026 | COT - HCBU - Excavation/Rebar/Zoning | Canceled | Canceled per contractor. 1/21/2026 | |
| 01/23/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Loading dock area (North), 11 load leveling pads. Ok to place concrete in progress areas. | |
| 02/19/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Loading dock area; East side retaining wall footing: approximately 60’. Ok to place concrete in progress areas. | |
| 03/02/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Slab footings are in place with #4 rebar. Concrete to be placed in the toe-down footing system. | |
| 05/28/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Partial pass. South small section of trench drain channels approved for concrete. 5/28/2026 | |
| 06/03/2026 | COT - HCBU - Excavation/Rebar/Zoning | Canceled | ||
| 10/02/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 10-2-25: reinforcement for front dock footings verified per schedule & details on S400. Okay for concrete placement at progress areas. | |
| 10/07/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 10/7/25 Partial pass on progress areas. North end of existing building. |
|
| 10/17/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 10-17-25: partial pass for East footing. Reinforcement verified per detail's S200 & S400. Okay for concrete placement at progress areas. | |
| 11/04/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Total of 9 columns on A line 15-8. Bolts in place per approved plans. Clearances approved around forms. Okay for concrete placement. 11/4/2025 |