Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
08/17/2022
Applicant:
Description:
INTERIOR RENOVATION OF PORTION OF BUILDING TO CREATE NEW SECURE AREASIN (E) OFFICE AREAS.

Permit Reviews

Permit Number - T22CM06325
Permit Status: Complete
Permit Description: INTERIOR RENOVATION OF PORTION OF BUILDING TO CREATE NEW SECURE AREASIN (E) OFFICE AREAS.
Start Date Submittal Complete Date Status  
08/17/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 09/21/2022 COMPLETED Review Details
10/11/2022 RESUBMITTAL 10/12/2022 ACTIVE Review Details
10/27/2022 COMMERCIAL REVIEW - FULL v.1 12/06/2022 APPROVED Review Details
06/22/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/27/2023 APPROVED Review Details
02/21/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/22/2024 APPROVED Review Details
02/07/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/08/2024 APPROVED Review Details

Conditions

Permit Number - T22CM06325
Permit Status: Complete
Permit Description: INTERIOR RENOVATION OF PORTION OF BUILDING TO CREATE NEW SECURE AREASIN (E) OFFICE AREAS.
Date Description Comments
11/09/2022 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
11/09/2022 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM06325
Permite Description: INTERIOR RENOVATION OF PORTION OF BUILDING TO CREATE NEW SECURE AREASIN (E) OFFICE AREAS.
Total Outstanding Inspections - 18
Last Inspection Date Description Inspector Results Comments
11/22/2022 COT - LCPL - Rough Soil N/A Partial Pass under groung ok, partial pass until plans have been submitted for “as built” plumbing.
12/09/2022 COT - HCPL - Plumbing Intermediate N/A Canceled
12/09/2022 COT - LCME - Mechanical Intermediate N/A Partial Pass Corridor. G0550.
12/09/2022 COT - HCEL - Electrical Progress N/A Canceled
12/09/2022 COT - HCEL - Electrical Intermediate N/A Canceled
03/03/2023 COT - HCBU - Framing N/A Partial Pass 3/3/23. Room J0605
02/17/2023 COT - HCBU - Interior Shear Bracing N/A Partial Pass room D0605
12/09/2022 COT - HCPL - Plumbing Progress N/A Canceled
04/12/2023 COT - HCME - Hydronic Piping N/A Partial Pass See notes in mechanical progress
02/09/2023 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass Room L0600
03/16/2023 COT - LCME - Mechanical Progress N/A Partial Pass 5/15/23. Room B0500, corridor, M0500, heating water supply, and return. Hard duct in room D0605..
12/09/2022 COT - HCEL - Electrical Above Ceiling N/A Partial Pass Corridor G0550.
04/26/2023 COT - HCBU - Building Above Ceiling N/A Partial Pass 4/25/2023. All supplemental rooms in B0500.
07/14/2023 COT - HCBU - Building Final N/A Partial Pass 7/13/23. Partial approval pending fire inspection. Ok for Level 4 TCO
07/14/2023 COT - FCON - Fire - Final N/A Partial Pass Phases 1 A&B approved for level 4 TCO.
07/14/2023 COT - FCON - Alarm - Final N/A Partial Pass Phase 1 A&B approved
05/30/2023 COT - FCON - Sprinkler - Final N/A Partial Pass Phase 1A approved OK for level 3 TCO
FCON – Fire – Intermediate N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM06325
Permit Description: INTERIOR RENOVATION OF PORTION OF BUILDING TO CREATE NEW SECURE AREASIN (E) OFFICE AREAS.
Total Completed Inspections - 8
Date Description Inspector Results Comments
07/14/2023 COT - HCBU - Building Above Ceiling Passed pass
07/14/2023 COT - HCME - Mechanical Final Passed 7/13/23. Pass
07/14/2023 COT - HCPL - Plumbing Final Passed 7/13/23. Pass
07/14/2023 COT - HCEL - Electrical Final Passed 7/13/23. Pass
02/02/2024 COT - HCBU - Building Final Passed Partial pass. Ok for TCO Level 3

5/31/23. Partial approval for phase 1A. Level 3 TCO.

7/13/23. Partial approval pending fire inspection. Ok for Level 4 TCO

2/2/24: Level 4 TCO for all of phase 1, Level 3 TCO for all of phase 2, pending Fire final and Test&Balance report.
02/02/2024 COT - FCON - Fire - Final Passed
02/02/2024 COT - FCON - Alarm - Final Passed
02/02/2024 COT - FCON - Sprinkler - Final Passed