Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCME - Mechanical Progress
Permit Number - T22CM06325
Inspection Description - COT - LCME - Mechanical Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/10/2023 | COT - LCME - Mechanical Progress | Partial Pass | copper lines for VAV system. In room B0500. | |
01/18/2023 | COT - LCME - Mechanical Progress | Partial Pass | room M0600 Corridor wall and corridor K | |
02/02/2023 | COT - LCME - Mechanical Progress | Partial Pass | room G0500 | |
02/06/2023 | COT - LCME - Mechanical Progress | Partial Pass | corridor, H0615 to F0620 And B0500, the AV a 4–12 and 4–13 corridor B0510. | |
02/17/2023 | COT - LCME - Mechanical Progress | Partial Pass | Room number C0550 and C0555 | |
02/22/2023 | COT - LCME - Mechanical Progress | Partial Pass | Corredor D0600, and corridor E0600. | |
02/27/2023 | COT - LCME - Mechanical Progress | Partial Pass | Hard duct in room D0610, C0555 and be 0505. | |
03/03/2023 | COT - LCME - Mechanical Progress | Partial Pass | 3/3/23. Room B0500 hard duck complete. Room D0620. Corridor D0615, VAV 4–6. | |
03/08/2023 | COT - LCME - Mechanical Progress | Partial Pass | 3/8/23. 24 x 24 duct in Corredor B0510. Chilled water, supply and return, main Corredor, E, line and K line. | |
03/16/2023 | COT - LCME - Mechanical Progress | Partial Pass | 5/15/23. Room B0500, corridor, M0500, heating water supply, and return. Hard duct in room D0605.. | |
03/19/2023 | COT - LCME - Mechanical Progress | Partial Pass | Room J0600 | |
03/29/2023 | COT - LCME - Mechanical Progress | Partial Pass | 3/28/23. Corridor F0620, VAV, 4-5, 4-58. Room D0500 | |
04/02/2023 | COT - LCME - Mechanical Progress | Partial Pass | 3/30/23. Hydronic piping in Corridor E0600, VA V 4–5 and corridor D06152 VAV 4-8, D0300. Duct J0605 |
|
04/07/2023 | COT - LCME - Mechanical Progress | Partial Pass | 4/07/23. Room D0605. Partial east side only room B0500. | |
04/12/2023 | COT - LCME - Mechanical Progress | Partial Pass | 4/12/23. Corridor G0550, columns, N to E & K corridor. AVA number 4–14. | |
04/26/2023 | COT - LCME - Mechanical Progress | Partial Pass | 4/25/2023. VAV-2_13, VAV-2-23 and VAV 4-58. | |
05/05/2023 | COT - LCME - Mechanical Progress | Partial Pass | 5/4/23. M0605, L0605, L0600, M0500, H0615, J0610. | |
05/13/2023 | COT - LCME - Mechanical Progress | Partial Pass | 5/12/23. Corredor's. H0616, F0620, 0600, D0615 and D0600. | |
05/23/2023 | COT - LCME - Mechanical Progress | Partial Pass | 5/22/23. Above ceiling room D0500. | |
05/30/2023 | COT - LCME - Mechanical Progress | Partial Pass | 5/26/23. Corridor 1B. OK for level 3 TCO | |
06/13/2023 | COT - LCME - Mechanical Progress | Partial Pass | 6/12/23. Room D0500 | |
12/09/2022 | COT - LCME - Mechanical Progress | Canceled | ||
12/16/2022 | COT - LCME - Mechanical Progress | Partial Pass | room L0500 and main Corredor duct 72 x 36“ |