Permit: T22CM05879
Permit Details
Apply Date:
08/02/2022
Applicant:
Ron Barter
Description:
New Hyundai Sales & Parts Building
Permit Reviews
Permit Number - T22CM05879
Permit Status: Complete
Permit Description: New Hyundai Sales & Parts Building
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/02/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/08/2022 | COMPLETED |
09/27/2022 | RESUBMITTAL | 10/12/2022 | COMPLETED |
12/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/05/2024 | REQUIRES RESUBMIT |
07/24/2024 | COMMERCIAL REVIEW - FULL v.2 | 08/21/2024 | APPROVED |
01/06/2023 | COMMERCIAL REVIEW - FULL v.1 | 01/09/2023 | APPROVED |
08/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/22/2024 | APPROVED |
09/12/2024 | RESTAMP - COMMERCIAL v.1 | 09/16/2024 | APPROVED |
12/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/18/2024 | APPROVED |
08/21/2024 | RESTAMP - COMMERCIAL v.1 | 08/21/2024 | APPROVED |
06/11/2024 | COMMERCIAL REVIEW - FULL v.1 | 07/16/2024 | REQUIRES RESUBMIT |
12/09/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/10/2024 | APPROVED |
Conditions
Permit Number - T22CM05879
Permit Status: Complete
Permit Description: New Hyundai Sales & Parts Building
Date | Description | Comments |
---|---|---|
08/22/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
09/10/2024 | SHOP DRAWINGS REQUIRED FOR FIRE ALARM. | |
09/10/2024 | SHOP DRAWINGS REQUIRED FOR FIRE SPRINKLERS. | |
09/10/2024 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
09/10/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
09/10/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
09/10/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
09/10/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
09/10/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
09/10/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
09/10/2024 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
09/10/2024 | SPECIAL INSPECTION IS REQUIRED FOR STEEL. | |
09/10/2024 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05879
Permite Description: New Hyundai Sales & Parts Building
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/12/2022 | COT - LCME - Mechanical Final | N/A | Re-inspection required | {Activity date: 10/12/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION} |
10/12/2022 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | {Activity date: 10/12/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION} |
05/30/2023 | COT - HCEL - Electrical Progress | N/A | Partial Pass | approved for secondary lines from transformer to SES |
07/30/2024 | ENGR Engineering Final | N/A | Partial Pass | need a bike rack? |
08/15/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | OK for TCO level 4 for showroom, sales and parts building., |
11/22/2024 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | |
07/13/2023 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05879
Permit Description: New Hyundai Sales & Parts Building
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/05/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
08/04/2023 | COT - HCPL - Plumbing Progress | Passed | ||
10/10/2023 | COT - HCBU - Preslab | Passed | 10/10/23: second floor deck slab ok to pour (reinforcement per plan pg.S103 note 1) | |
10/10/2023 | COT - HCBU - Roof Nailing | Passed | 10/10/23: second floor deck slab ok to pour (reinforcement per plan pg.S103 note 1), roof nailing approved by special inspection. | |
12/08/2023 | COT - HCBU - Building Progress | Passed | ||
02/29/2024 | COT - BULD - SWG Clearance | Passed | Approved gas piping and pressure test, SWG Clearance is required | |
03/07/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 3/7/2024 | |
03/07/2024 | COT - HCEL - Electrical Progress | Passed | ||
08/07/2024 | ENGR Engineering Final | Passed | ||
08/16/2024 | COT - HCBU - TCO | Passed | Ok for level 4 TCO, please adjust all door closers | |
08/21/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
08/29/2024 | COT - HCPL - Rough Soil | Passed | ||
09/11/2024 | COT - HCPL - Sewer | Passed | ||
09/30/2024 | COT - HCEL - Electrical Intermediate | Passed | 9/30/24: EV STORAGE restroom and brake room okay to cover in wall. | |
09/30/2024 | COT - HCME - Mechanical Intermediate | Passed | 9/30/24: EV STORAGE restroom and brake room okay to cover in wall. | |
09/30/2024 | COT - HCBU - Framing | Passed | 9/30/24: EV STORAGE restroom and brake room okay to cover in wall. | |
09/30/2024 | COT - HCME - Mechanical Above Ceiling | Passed | 9/30/24: EV STORAGE restroom and brake room okay to cover in wall. | |
09/30/2024 | COT - HCME - Mechanical Progress | Passed | 9/30/24: EV STORAGE restroom and brake room okay to cover in wall. | |
10/11/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
10/14/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
10/28/2024 | COT - HCEL - Electrical Above Ceiling | Passed | Room # 131. 129A. Approved. Okay to proceed progress areas. 10/28/2024 | |
10/28/2024 | COT - HCPL - Gas Pressure Test | Passed | Gas line feeding air handler for break room EV room and two restrooms. Approved and on test. 10/28/2028 | |
11/13/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
11/20/2024 | COT - FCON - Sprinkler - Final | Passed | ||
11/20/2024 | COT - HCEL - Electrical Final | Passed | ||
11/20/2024 | COT - HCPL - Gas Final | Passed | ||
11/20/2024 | COT - HCPL - Plumbing Final | Passed | ||
11/22/2024 | COT - HCME - Mechanical Final | Passed | ||
11/22/2024 | COT - HCBU - Building Final | Passed | ||
11/22/2024 | COT - FCON - Alarm - Final | Passed | Passed by C Basaldua on 11/21/2024 | |
11/22/2024 | COT - FCON - Fire - Final | Passed | ||
11/22/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
11/22/2024 | COT - HCBU - Masonry Pregrout | Passed |