Permit: T22CM02376
Permit Details
Apply Date:
03/31/2022
Applicant:
vance goodman
Description:
R-LAUNDRY ROOM; GARAGE and PORCH ADDITION
Permit Reviews
Permit Number - T22CM02376
Permit Status: Complete
Permit Description: R-LAUNDRY ROOM; GARAGE and PORCH ADDITION
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/31/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 04/28/2022 | COMPLETED |
05/10/2022 | RESUBMITTAL | 05/13/2022 | COMPLETED |
02/10/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/10/2023 | APPROVED |
04/14/2023 | RESIDENTIAL NEW DWELLING v.1 | 05/11/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM02376
Permit Status: Complete
Permit Description: R-LAUNDRY ROOM; GARAGE and PORCH ADDITION
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/13/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Conditions
Permit Number - T22CM02376
Permit Status: Complete
Permit Description: R-LAUNDRY ROOM; GARAGE and PORCH ADDITION
Date | Description | Comments |
---|---|---|
05/13/2022 | SHOP DRAWINGS REQUIRED FOR TRUSS DRAWINGS |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM02376
Permite Description: R-LAUNDRY ROOM; GARAGE and PORCH ADDITION
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/18/2022 | RSME - Mechanical Progress | N/A | Canceled | {Activity date: 05/18/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
02/01/2023 | COT - RSBU - Stem Wall/Retaining Wall | N/A | Not Applicable | |
10/26/2022 | COT - RSPL - Gas Pressure Test | N/A | Not Ready | |
10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
04/07/2023 | COT - RSEL - Electrical Final | N/A | Not Ready | |
04/12/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | Partial per intermediates 4-7-23: 1-Gas line is not per approved plans; and has changed from tank to tankless. 2-No test on gas, nor DWV piping. 3-Install vertical fire blocking at 10' max spacing at all furr-out walls. Per R302.11#1.2. 4-Complete fireblocking per R302.11.1. 5-Seal all fireblocking. 4/12/23: provide new revision to plans for gas line to tankless water heater and change pipe to 3/4" ID. OK to proceed at risk. |
02/22/2023 | COT - RSBU - Preslab | N/A | Partial Pass | top-out grout lift for garage/addition |
04/07/2023 | COT - LCBU - Framing | N/A | Re-inspection required | 4-7-23: 1-Gas line is not per approved plans; and has changed from tank to tankless. 2-No test on gas, nor DWV piping. 3-Install vertical fire blocking at 10' max spacing at all furr-out walls. Per R302.11#1.2. 4-Complete fireblocking per R302.11.1. 5-Seal all fireblocking. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM02376
Permit Description: R-LAUNDRY ROOM; GARAGE and PORCH ADDITION
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/25/2022 | COT - RSEL - Service Relocation | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP. INCR clearance code for TEP. Called in at 2:02.} | |
05/25/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE INCR} | |
01/18/2023 | COT - RSPL - Rough Soil | Passed | ||
01/18/2023 | COT - RSPL - Sewer | Passed | ||
02/01/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
03/07/2023 | COT - RSBU - Roof Nailing | Passed | ||
03/07/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
07/18/2023 | RSBU - Building Final | Passed | ||
07/18/2023 | COT - RSPL - Yard Water Line | Passed | ||
07/18/2023 | COT - RSPL - Plumbing Final | Passed | ||
07/18/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
07/18/2023 | COT - RSME - Mechanical Final | Passed | ||
07/18/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
07/18/2023 | COT - RSEL - Electrical Final | Passed | ||
07/18/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
07/18/2023 | COT - RSBU - Preslab | Passed | ||
07/18/2023 | COT - LCBU - Framing | Passed |