Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - RSEL - Electrical Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | COT - RSEL - Electrical Final | Not Ready | ||
| 04/07/2023 | COT - RSEL - Electrical Final | Not Ready | ||
| 04/12/2023 | COT - RSEL - Electrical Final | Partial Pass | Partial per intermediates 4-7-23: 1-Gas line is not per approved plans; and has changed from tank to tankless. 2-No test on gas, nor DWV piping. 3-Install vertical fire blocking at 10' max spacing at all furr-out walls. Per R302.11#1.2. 4-Complete fireblocking per R302.11.1. 5-Seal all fireblocking. 4/12/23: provide new revision to plans for gas line to tankless water heater and change pipe to 3/4" ID. OK to proceed at risk. |
|
| 07/18/2023 | COT - RSEL - Electrical Final | Passed |