Permit Details

Status:
Complete
Type:
Commercial Building
Address:
1401 W GLENN ST
Address NEW:
1401 W GLENN ST
Apply Date:
01/11/2022
Applicant:
Description:
2nd Party - New one story 9,600 s.f. masonry walls and wood roof structure plus 3,200 s.f. of exterior steel can

Permit Reviews

Permit Number - T22CM00211
Permit Status: Complete
Permit Description: 2nd Party - New one story 9,600 s.f. masonry walls and wood roof structure plus 3,200 s.f. of exterior steel can
Start Date Submittal Complete Date Status  
01/11/2022 COMMERCIAL - NEW 03/02/2022 COMPLETED Review Details
07/01/2022 RESUBMITTAL 07/19/2022 COMPLETED Review Details
04/12/2024 COMMERCIAL REVIEW - FULL v.1 05/13/2024 APPROVED Review Details
04/02/2024 COMMERCIAL REVIEW - FULL v.1 04/08/2024 REQUIRES RESUBMIT Review Details
12/18/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/18/2024 REQUIRES RESUBMIT Review Details
12/26/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 12/30/2024 APPROVED Review Details
05/13/2024 RESTAMP - COMMERCIAL v.1 05/14/2024 APPROVED Review Details
04/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 04/18/2025 REQUIRES RESUBMIT Review Details
07/06/2023 RESTAMP - COMMERCIAL v.1 07/10/2023 APPROVED Review Details
04/21/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.3 04/24/2025 APPROVED Review Details
04/03/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/15/2025 REQUIRES RESUBMIT Review Details
06/06/2023 COMMERCIAL REVIEW - FULL v.1 07/06/2023 APPROVED Review Details

Conditions

Permit Number - T22CM00211
Permit Status: Complete
Permit Description: 2nd Party - New one story 9,600 s.f. masonry walls and wood roof structure plus 3,200 s.f. of exterior steel can
Date Description Comments
05/14/2024 AIR BALANCING REPORT IS REQUIRED.
05/14/2024 COMMISSIONING REPORT IS REQUIRED.
04/24/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/24/2025 Masonry Inspection Report submittal review is required.
05/14/2024 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
05/14/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
05/14/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
05/14/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
05/14/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM00211
Permite Description: 2nd Party - New one story 9,600 s.f. masonry walls and wood roof structure plus 3,200 s.f. of exterior steel can
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
11/28/2023 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 9/5/23 partial for footer only, need grounding for building and UFER
9/25/23: partial good to continue to second lift special inspection by saeco was done on the 21st
11/6/23 next lift good for grout, 17 to 20'
11/14/23 partial for grout last lift
11/28/23: reinforcement for column footings (F2) per plan.S1.4
05/31/2024 COT - HCPL - Plumbing Progress N/A Partial Pass
08/23/2024 COT - FCON - Fire - Final N/A Partial Pass Items that still need to be addressed FDC sign, FACP sign, Knox box, EM lights and fire extinguisher. Ok to obtain TCO level 2.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM00211
Permit Description: 2nd Party - New one story 9,600 s.f. masonry walls and wood roof structure plus 3,200 s.f. of exterior steel can
Total Completed Inspections - 28
Date Description Inspector Results Comments
09/25/2023 COT - HCBU - Building Progress Passed 9/25/23: partial good to continue to second lift special inspection by saeco was done on the 21st
01/11/2024 COT - HCBU - Exterior Clips/Sheathing Passed
01/11/2024 COT - HCBU - Roof Nailing Passed
02/09/2024 COT - HCPL - Rough Soil Passed Okay to backfill. Shading required. 2/9/2024
04/11/2024 COT - HCBU - Preslab Passed Rebar per plan at all door openings and main pad. Okay for concrete placement. 4/11/2024
04/11/2024 COT - HCBU - Excavation/Rebar/Zoning Passed Rebar per plan at all door openings and main pad. Okay for concrete placement.
Footing for steel post approved. 4/11/2024
04/11/2024 COT - HCEL - Electrical Underground Passed
04/11/2024 COT - HCBU - Stem Wall/Retaining Wall Passed
06/07/2024 BULD - Electrical Clearance Passed Clearance for TEP ECO. UNIT #2. 6/7/2024
07/02/2024 COT - HCBU - Framing Passed
07/02/2024 COT - HCBU - Interior Shear Bracing Passed
07/02/2024 COT - HCEL - Electrical Intermediate Passed
07/02/2024 COT - HCME - Mechanical Intermediate Passed
07/02/2024 COT - HCPL - Plumbing Intermediate Passed
07/02/2024 COT - HCPL - Plumbing Progress Passed
08/27/2024 COT - HCEL - Electrical Final Passed
08/27/2024 COT - HCME - Mechanical Progress Passed
08/27/2024 COT - HCEL - Outdoor Lighting Passed
08/27/2024 COT - HCEL - Electrical Progress Passed
08/29/2024 COT - HCBU - TCO Passed
08/29/2024 COT - HCME - Mechanical Final Passed
08/29/2024 COT - HCPL - Plumbing Final Passed
08/29/2024 COT - BULD - SWG Clearance Passed
10/23/2024 TRSP - ROW - Final/Close-Out Passed
11/07/2024 COT - HCBU - Building Final Passed
11/07/2024 COT - HCBU - CofO Passed
12/02/2024 COT - FCON - Fire - Final Passed
12/02/2024 ENGR Engineering Final Passed