Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 08/29/2024 |
ENGR Engineering Final
|
|
Partial Pass |
Call Dr. needs to complete the sidewalk parking at the water harvesting and the basin areas |
| 10/23/2024 |
ENGR Engineering Final
|
|
Partial Pass |
Contractor continuing to work on the rip wrap on the south end of the building. And forming the wedge curb on the east side of the road. |
| 11/07/2024 |
ENGR Engineering Final
|
|
Partial Pass |
Contractor needs to complete in placing the DG along the roadway on the West End |
| 12/02/2024 |
ENGR Engineering Final
|
|
Passed |
|