Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - T22CM00211
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/20/2024 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9/5/23 partial for footer only, need grounding for building and UFER 9/25/23: partial good to continue to second lift special inspection by saeco was done on the 21st 11/6/23 next lift good for grout, 17 to 20' 11/14/23 partial for grout last lift 11/28/23: reinforcement for column footings (F2) per plan.S1.4 3/20/24: trench drain reinforcement per plan ok to pour. |
|
04/11/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Rebar per plan at all door openings and main pad. Okay for concrete placement. Footing for steel post approved. 4/11/2024 |
|
09/05/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9/5/23 partial for footer only, need grounding for building and UFER | |
09/06/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Electrical grounding in place (ufer). Ok to place concrete in progress areas. | |
COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9/25/23: partial good to continue to second lift special inspection by saeco was done on the 21st | ||
10/02/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | CMU walls at 0’ - 4’. Ok to grout progress areas. | |
10/09/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Masonry pre-grout of CMU walls at,4’ - 8’. Ok to grout progress areas with proper rebar placement. | |
10/16/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | CMU walls at 8’ - 12’ above finished floor level. Ok to grout progress areas. | |
10/23/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | CMU Walls at 12’ - 16’. Ok to grout progress areas. Ensure,all large openings have double rebar at openings | |
11/06/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 11/6/23 next lift good for grout, 17 to 20' | |
11/14/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 11/14/23 partial for grout last lift | |
11/28/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9/5/23 partial for footer only, need grounding for building and UFER 9/25/23: partial good to continue to second lift special inspection by saeco was done on the 21st 11/6/23 next lift good for grout, 17 to 20' 11/14/23 partial for grout last lift 11/28/23: reinforcement for column footings (F2) per plan.S1.4 |