Permit: T21CM09907
Permit Details
Apply Date:
12/28/2021
Applicant:
Kaye Bagley
Description:
3 story Climate controlled self storage facility with exterior canopy covered RV storage and site im
Permit Reviews
Permit Number - T21CM09907
Permit Status: Complete
Permit Description: 3 story Climate controlled self storage facility with exterior canopy covered RV storage and site im
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/12/2022 | RESUBMITTAL | 05/02/2022 | COMPLETED |
05/12/2022 | RESUBMITTAL | 05/27/2022 | COMPLETED |
08/19/2022 | REVISION - - 1ST | 09/21/2022 | COMPLETED |
09/27/2022 | REVISION - - 1ST | 09/30/2022 | COMPLETED |
10/03/2022 | REVISION - - 1ST | 10/05/2022 | COMPLETED |
12/28/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 02/03/2022 | COMPLETED |
04/30/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 05/02/2024 | REQUIRES RESUBMIT |
04/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/18/2024 | REQUIRES RESUBMIT |
06/03/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/04/2024 | APPROVED |
05/09/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 05/20/2024 | APPROVED |
11/17/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/17/2022 | APPROVED |
Conditions
Permit Number - T21CM09907
Permit Status: Complete
Permit Description: 3 story Climate controlled self storage facility with exterior canopy covered RV storage and site im
Date | Description | Comments |
---|---|---|
05/23/2024 | AIR BALANCING REPORT IS REQUIRED. | |
03/22/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
03/22/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
04/12/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
03/22/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
03/22/2024 | SHOP DRAWINGS REQUIRED FOR ALTERNATE STAIR DESIGN | |
03/22/2024 | SHOP DRAWINGS REQUIRED FOR ELEVATOR | |
03/22/2024 | SHOP DRAWINGS REQUIRED FOR FIRE ALARM | |
03/22/2024 | SHOP DRAWINGS REQUIRED FOR FIRE SPRINKLER | |
03/22/2024 | SHOP DRAWINGS REQUIRED FOR SIGNAGE | |
04/12/2024 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
03/22/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
01/30/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
03/22/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
04/12/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. | |
03/22/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
03/22/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
05/23/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM09907
Permite Description: 3 story Climate controlled self storage facility with exterior canopy covered RV storage and site im
Total Outstanding Inspections - 21
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
10/26/2022 | COT - FCON - Underground Pressure | N/A | Not Ready | |
05/02/2023 | COT - HCPL - Sewer | N/A | Partial Pass | 5-2-23: From Building North to lateral, and approx 40 Feet East for RV run. |
06/06/2023 | COT - HCBU - Framing | N/A | Partial Pass | 3-17-23: Basement. 4-25-23: Level one; North half. 6/6/23: level 2 all framing, level 3 deck. |
01/05/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
12/19/2023 | COT - HCEL - Electrical Final | N/A | Not Ready | |
01/05/2024 | COT - HCPL - Plumbing Final | N/A | Canceled | |
08/29/2023 | COT - HCPL - Plumbing Progress | N/A | Canceled | |
01/13/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | Cast in place wall on West side. |
10/31/2023 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | 9/11/23: Den-shield on west wall complete. 10/31/23: lath on south end of building nailing per schedule. |
03/18/2024 | COT - HCBU - Sustainability | N/A | Not Applicable | |
08/23/2023 | COT - HCEL - Electrical Progress | N/A | Partial Pass | Bathrooms level one. |
08/02/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | |
03/18/2024 | COT - HCPL - Backwater Valve | N/A | Not Applicable | |
03/18/2024 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | |
05/05/2023 | COT - HCPL - Rough Soil | N/A | Partial Pass | 5-5-23: Water test on exterior. |
02/15/2023 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 1st lift of South site wall. 17’ 4” at West stair well. |
10/26/2022 | COT - FCON - Fire - Final | N/A | Partial Pass | Waiting for approval of BDA fire alarm permit. Everything else is approved. |
09/29/2023 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | 9/29/23: level 1 & 2 restrooms above ceiling approved. |
08/23/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Canceled | |
04/28/2023 | COT - HCBU - Preslab | N/A | Partial Pass | 4-28-23: Level Two, North half. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM09907
Permit Description: 3 story Climate controlled self storage facility with exterior canopy covered RV storage and site im
Total Completed Inspections - 33