Inspection Status: Not Ready
Inspection History: COT - HCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - HCBU - Building Progress |
|
Not Ready |
|
| 01/05/2023 |
COT - HCBU - Building Progress |
|
Canceled |
needed consultation. |
| 01/12/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
|
| 01/13/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Cast in place wall on West side. |
| 01/18/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Epoxy of vertical dowels at North wall of North stairs. |
| 01/20/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
3 rd lift at North Stairwell. |
| 01/26/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
West half of South wall. |
| 01/27/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Fence footings. |
| 02/01/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
Cast in place basement walls; Southeast corner. |
| 02/06/2023 |
COT - HCBU - Building Progress |
|
Partial Pass |
South wall near elevator. |
| 03/18/2024 |
COT - HCBU - Building Progress |
|
Passed |
|
| 08/23/2023 |
COT - HCBU - Building Progress |
|
Passed |
Dens glass on parapet walls. Level one insulation. |
| 11/22/2022 |
COT - HCBU - Building Progress |
|
Partial Pass |
Stemwall for basement; North side. |
| 12/28/2022 |
COT - HCBU - Building Progress |
|
Partial Pass |
basement east, west AND south stem wall grid lines K TO S.5 AND GRID LINE 1 TO 13 AND K.5 TO T5 |