Permit: T21CM08621
Permit Details
Apply Date:
11/02/2021
Applicant:
Michelle Virgin
Description:
Shell permit Construction of a new one story building of 9,015 s.f. with an interior build out of 2,752 s.f. for
Permit Reviews
Permit Number - T21CM08621
Permit Status: Complete
Permit Description: Shell permit Construction of a new one story building of 9,015 s.f. with an interior build out of 2,752 s.f. for
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/19/2022 | RESUBMITTAL | 05/16/2022 | COMPLETED |
05/24/2022 | RESUBMITTAL | 06/03/2022 | COMPLETED |
06/22/2022 | RESUBMITTAL | 08/01/2022 | COMPLETED |
11/02/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 12/08/2021 | COMPLETED |
11/21/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/14/2022 | APPROVED |
12/05/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/05/2023 | APPROVED |
02/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/14/2023 | APPROVED |
02/26/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/28/2024 | APPROVED |
01/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/16/2024 | APPROVED |
Conditions
Permit Number - T21CM08621
Permit Status: Complete
Permit Description: Shell permit Construction of a new one story building of 9,015 s.f. with an interior build out of 2,752 s.f. for
Date | Description | Comments |
---|---|---|
06/24/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
06/24/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
06/24/2022 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
06/24/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
06/24/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
06/24/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
06/24/2022 | SPECIAL INSPECTION FOR SHOTCRETE IS REQUIRED. | |
06/24/2022 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
06/24/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
06/24/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
06/24/2022 | SHOP DRAWINGS REQUIRED FOR SPRINKLERS | |
06/24/2022 | SHOP DRAWINGS REQUIRED FOR I JOISTS | |
06/24/2022 | SHOP DRAWINGS REQUIRED FOR TRUSS CALCS | |
08/01/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required | |
08/01/2022 | DO NOT ISSUE THIS PERMIT UNTIL DP21-0263 HAS BEEN ISSUED. | |
01/12/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
01/12/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM08621
Permite Description: Shell permit Construction of a new one story building of 9,015 s.f. with an interior build out of 2,752 s.f. for
Total Outstanding Inspections - 12
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/08/2023 | COT - LCBU - Building Progress | N/A | Not Applicable | |
09/13/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Applicable | |
09/13/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Applicable | |
10/16/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
06/22/2023 | COT - HCPL - Yard Water Line | N/A | Partial Pass | 6-22-23: Line from building to future backflow location. |
11/30/2023 | COT - LCBU - Masonry Pregrout | N/A | Not Applicable | |
07/31/2023 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | 7/31/23: Not ready for inspection. |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
10/27/2022 | COT - LCBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM08621
Permit Description: Shell permit Construction of a new one story building of 9,015 s.f. with an interior build out of 2,752 s.f. for
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/06/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
05/12/2023 | COT - LCBU - Roof Nailing | Passed | ||
05/12/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
05/24/2023 | COT - LCPL - Plumbing Roof Drains | Passed | 5/24/23: 5 sets of roof drains approved to cover. | |
07/11/2023 | COT - LCPL - Sewer | Passed | ||
07/11/2023 | COT - LCPL - Rough Soil | Passed | ||
07/11/2023 | COT - LCPL - Backwater Valve | Passed | ||
09/13/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
10/16/2023 | BULD - Electrical Clearance | Passed | Approved new service for shell building, ECO Clearance to TEP is required for the "Owners Panel" | |
10/27/2023 | COT - LCEL - Electrical Underground | Passed | Conduit for panels A & B March 22nd: underground coundit on exterior south side of building and several stub-ins on same side April 4th: east half (DMC) 10/27/23:grounding for 2 light pole bases per plan. |
|
10/27/2023 | COT - LCEL - Electrical Progress | Passed | ||
10/27/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | April 4th: east half (DMC) 4/7/23: west half of building. Interior pour strip on north & east & south sides. Rebar per plan. 10/27/23: 2 light pole bases approved. |
|
11/30/2023 | COT - HCPL - Yard Water Line | Passed | ||
11/30/2023 | COT - LCME - Mechanical Final | Passed | ||
11/30/2023 | COT - LCME - Mechanical Progress | Passed | ||
11/30/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
11/30/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
11/30/2023 | COT - LCEL - Electrical Final | Passed | ||
11/30/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
11/30/2023 | COT - LCBU - Sustainability | Passed | ||
11/30/2023 | COT - LCBU - Framing | Passed | ||
11/30/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
11/30/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
11/30/2023 | COT - LCBU - Preslab | Passed | ||
11/30/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
11/30/2023 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
11/30/2023 | COT - LCPL - Plumbing Progress | Passed | ||
11/30/2023 | COT - LCPL - Plumbing Final | Passed | ||
11/30/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
12/01/2023 | COT - FCON - Sprinkler - Final | Passed | ||
12/05/2023 | COT - FCON - Fire - Final | Passed | ||
12/05/2023 | COT - FCON - Alarm - Final | Passed | ||
12/13/2023 | COT - LCBU - Building Final | Passed | Shell building and tenant improvements are completed. Okay to issue Level 4 Certificate of Occupancy. |