Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCPL - Rough Soil
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCPL - Rough Soil | Not Ready | ||
| 03/08/2023 | COT - LCPL - Rough Soil | Partial Pass | All new soil pipe in the east half of building approved to cover. The building main drain in the west half approved to cover. | |
| 03/24/2023 | COT - LCPL - Rough Soil | Partial Pass | All new soil pipe in the east half of building approved to cover. The building main drain in the west half approved to cover. March 24th: added floor drain and sink relocation on north side. Water tested and approved. |
|
| 06/21/2023 | COT - LCPL - Rough Soil | Canceled | ||
| 07/11/2023 | COT - LCPL - Rough Soil | Passed |