Permit: T21CM07491
Permit Details
Apply Date:
09/16/2021
Applicant:
Description:
New free standing, residential, hotel use group building, sprinkled NFPA 13 throughout.
Permit Reviews
Permit Number - T21CM07491
Permit Status: Complete
Permit Description: New free standing, residential, hotel use group building, sprinkled NFPA 13 throughout.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/19/2022 | RESUBMITTAL | 02/18/2022 | COMPLETED |
03/10/2022 | RESUBMITTAL | 03/22/2022 | COMPLETED |
03/31/2022 | REVISION - - 1ST | 05/19/2022 | COMPLETED |
09/16/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/18/2021 | COMPLETED |
10/20/2022 | REVISION - - 2ND | 10/20/2022 | ACTIVE |
10/09/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/18/2023 | APPROVED |
07/10/2023 | COMMERCIAL PDSD SIMPLE REVIEW v.2 | 07/17/2023 | APPROVED |
10/29/2022 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 11/16/2022 | APPROVED |
12/12/2022 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 02/06/2023 | APPROVED |
07/07/2023 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 07/07/2023 | REQUIRES RESUBMIT |
03/21/2023 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 04/05/2023 | APPROVED |
11/22/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/22/2023 | APPROVED |
10/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/19/2023 | APPROVED |
Conditions
Permit Number - T21CM07491
Permit Status: Complete
Permit Description: New free standing, residential, hotel use group building, sprinkled NFPA 13 throughout.
Date | Description | Comments |
---|---|---|
03/21/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
03/21/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
03/21/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
03/21/2022 | SHOP DRAWINGS REQUIRED FOR ROOF TRUSSES | |
03/21/2022 | SHOP DRAWINGS REQUIRED FOR FLOOR TRUSSES | |
11/22/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM07491
Permite Description: New free standing, residential, hotel use group building, sprinkled NFPA 13 throughout.
Total Outstanding Inspections - 26
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
10/26/2022 | COT - FCON - Underground Flush | N/A | Not Applicable | |
10/26/2022 | COT - LCPL - Rough Soil | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Sewer | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Backwater Valve | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
02/01/2023 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | partial approval for third floor exhaust fans and associated ductwork |
01/23/2023 | COT - LCBU - Framing | N/A | Partial Pass | level 3 framing good. |
01/17/2023 | COT - LCBU - Exterior Clips/Sheathing | N/A | Not Ready | |
10/26/2022 | COT - FCON - Underground Pressure | N/A | Not Ready | |
01/23/2023 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | level 3 exterior shear walls are good. |
01/17/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
03/29/2023 | COT - LCME - Mechanical Progress | N/A | Partial Pass | Level #3. room units and elevator room |
04/04/2023 | COT - LCME - Mechanical Above Ceiling | N/A | Partial Pass | Rooms on Levels #3 & 4. |
05/11/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Partial Pass | Level #1, Rooms and corridors. |
05/11/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | Level #1, rooms and corridors. Ok to cover progress areas. |
05/18/2023 | COT - LCEL - Electrical Progress | N/A | Partial Pass | Exterior electric pad for in line and secondary power. Lines tone mandrel tested by TEP. Gas pressure test for in house laundry and outdoor grill. Ok to set commercial meter. |
05/26/2023 | COT - LCBU - Interior Shear Bracing | N/A | Partial Pass | 5/26/23: 1st floor wallboard approved |
04/05/2023 | COT - LCPL - Plumbing Progress | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
07/11/2023 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | Electric complete for Levels 2, 3, 4. Lines from TEP Transformer to building, awaiting disconnects and gear to be completed in order to energize system. |
09/21/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | |
10/26/2022 | COT - LCPL - Gas Pressure Test | N/A | Not Ready | |
10/09/2023 | COT - LCBU - Building Final | N/A | Partial Pass | 1sr floor; upper floors pending elevator approval. |
10/18/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Alarm shall be approved. Elevator keys shall be provided. |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM07491
Permit Description: New free standing, residential, hotel use group building, sprinkled NFPA 13 throughout.
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/01/2023 | COT - LCBU - Roof Nailing | Passed | ||
03/21/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
03/23/2023 | COT - LCBU - Preslab | Passed | All pre slab work has been completed. | |
03/23/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | Levels #1 - #4; Ok to cover exterior walls. | |
03/23/2023 | COT - HCBU - Interior Shear Bracing | Passed | Interior shear walls are in place. Sheet rock nailing to be approved by architect. | |
03/30/2023 | COT - LCEL - Electrical Underground | Passed | ||
05/26/2023 | COT - LCBU - Building Progress | Passed | ||
07/18/2023 | COT - LCEL - Electrical Final | Passed | Ok to energize building. Need electric clearance: Code: ECO. | |
08/01/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
10/18/2023 | FCON – OH Piping & Hydro | Passed | Passed by Will Motto on Fire Sprinkler Permit | |
08/31/2023 | COT - LCPL - Plumbing Final | Passed | ||
09/21/2023 | COT - RSPL - Sewer | Passed | 9/21/23: south end building sewer main sewer connection. | |
09/21/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
09/21/2023 | COT - LCPL - Plumbing Intermediate | Passed | 9/21/23: south end building sewer main sewer connection. | |
10/06/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
10/09/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
10/09/2023 | BULD - Electrical Clearance | Passed | ||
10/09/2023 | COT - LCME - Mechanical Final | Passed | ||
10/10/2023 | COT - FCON - Sprinkler - Final | Passed | ||
10/18/2023 | COT - LCBU - Building Final | Passed | Elevator inspection is completed and signed off on 10/17/2023. Okay to issue Certificate of Occupancy, once all other departments have signed off on permit. | |
10/19/2023 | COT - FCON - Fire - Final | Passed | ||
10/19/2023 | COT - FCON - Alarm - Final | Passed |