Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Not Ready
Inspection History: COT - LCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Preslab |
|
Not Ready |
|
| 10/26/2022 |
COT - LCBU - Preslab |
|
Not Ready |
|
| 02/01/2023 |
COT - LCBU - Preslab |
|
Partial Pass |
partial approval for entry and north side barbecue area column footers ok to place concrete |
| 02/14/2023 |
COT - LCBU - Preslab |
|
Partial Pass |
for BBQ PIT AND ENTRY COLUMNS IMBEDS, OK TO PLACE CONCRETE |
| 03/23/2023 |
COT - LCBU - Preslab |
|
Passed |
All pre slab work has been completed. |
| 11/04/2022 |
COT - LCBU - Preslab |
|
Partial Pass |
Approved Excavation and Footing Rebar only, pending pre-slab |
| 11/17/2022 |
COT - LCBU - Preslab |
|
Partial Pass |
Partial for pre-slab on the North end from gridline 1-8, okay for concrete placement |
| 11/29/2022 |
COT - LCBU - Preslab |
|
Passed |
Approved, okay to pour remaining building slab |