Inspection Status: Not Ready
Inspection History: COT - LCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
COT - LCPL - Plumbing Intermediate |
|
Not Ready |
|
| 06/15/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
Tubs and shower pans are under hydro test. Ok to drown water tests in all areas. |
| 07/11/2023 |
COT - LCPL - Plumbing Intermediate |
|
Partial Pass |
Plumbing complete for rooms on Levels 2, 3, 4. |
|
COT - LCPL - Plumbing Intermediate |
|
Passed |
9/21/23: south end building sewer main sewer connection. |