Inspection Status: Not Ready
Inspection History: COT - LCME - Mechanical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCME - Mechanical Progress |
|
Not Ready |
|
| 01/30/2023 |
COT - LCME - Mechanical Progress |
|
Partial Pass |
mechanical contractor has fire dampers installed and tested on 1st floor. exhaust fan ductwork for bathrooms is complete on 4th floor with fire caulking applied at penetrations of floors & ceilings. will schedule intermediate mechanical inspection and above ceiling inspection for Wednesday afternoon 2/1/2023. |
| 03/28/2023 |
COT - LCME - Mechanical Progress |
|
Partial Pass |
Level #3, Ok to one side interior walls. |
| 03/29/2023 |
COT - LCME - Mechanical Progress |
|
Partial Pass |
Level #3. room units and elevator room |