Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM06766
Permit Details
Apply Date:
08/19/2021
Applicant:
Tucson Expediting & Development
Description:
RETAIL
Architects:
- Amelia Elliott
Contractors:
- CHASSE BUILDING TEAM INC***APA***
Permit Reviews
Permit Number - T21CM06766
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/19/2021 | 3RD PARTY REVIEW - COMMERCIAL | 09/28/2021 | COMPLETED |
10/21/2021 | RESUBMITTAL - TI ALL | 11/22/2021 | COMPLETED |
11/22/2021 | RESUBMITTAL | 11/30/2021 | COMPLETED |
12/20/2021 | REVISION - - 1ST | 01/26/2022 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM06766
Permit Description: RETAIL
Total Completed Inspections - 47
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/21/2021 | REINFORCED MASONRY PRE-GROUT | TGAUSP | Approved | NR |
12/28/2021 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Approved, conduits under slab ok to backfill and prep slab. |
12/28/2021 | ELECTRIC - UFER | DMUNIZ | Approved | Approved |
12/28/2021 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | Partial, CMU Stem from GL A-D, 3-5 OK for grout placement, Note: Inspection required for CMU Dock wall finish. |
05/06/2022 | PLUMBING - PRE SLAB | TGAUSP | Approved | Approved |
05/06/2022 | BUILDING PRE-SLAB | TGAUSP | Approved | Approved, okay for concrete placement |
05/12/2022 | ROOF NAILING | TGAUSP | Approved | Approved for wood roofs and metal decking by special inspection |
05/12/2022 | EXT METAL CLIPS/EXT SHEATHING | TGAUSP | Approved | Approved |
05/12/2022 | PLUMBING - GAS PRESSURE TEST | TGAUSP | Approved | Approved |
05/12/2022 | ELECTRIC - CONSTRUCTION POWER | TGAUSP | Approved | Approved, please send RECN Clearance to TEP for the construction power. *Note - This 2nd clearance is for the existing panel addressed 4755 S. Calle Sara Cruz, Lot 14 Temp. |
06/08/2022 | SHEET ROCK NAILING | DMUNIZ | Approved | Approved |
06/17/2022 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Approved |
06/17/2022 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | Approved |
06/17/2022 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | Approved |
06/17/2022 | FRAMING | ESTEVENS | Approved | Approved |
06/28/2022 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE ECO |
06/28/2022 | ELECTRIC - CABLE DROP | TGAUSP | Approved | - Approved for 1000A SES panel, please send ECO Clearance to TEP |
06/30/2022 | MECHANICAL - HOODS | TGAUSP | Approved | Approved 1st and 2nd fire wraps, pending final |
07/15/2022 | ELECTRIC - PROGRESS | TGAUSP | Approved | - Approved for all interior panels, okay to test breakers and equipment |
08/17/2022 | MECHANICAL - ABOVE CEILING | TGAUSP | Approved | Approved |
08/17/2022 | MECHANICAL - PROGRESS | TGAUSP | Approved | Approved |
08/17/2022 | ELECTRIC - ABOVE CEILING | TGAUSP | Approved | Approved |
08/17/2022 | BUILDING - PROGRESS | TGAUSP | Approved | Approved |
08/17/2022 | PLUMBING - ABOVE CEILING | TGAUSP | Approved | Approved |
08/17/2022 | PLUMBING - PROGRESS | TGAUSP | Approved | Approved |
08/17/2022 | PLUMBING - ROUGH, SOIL | TGAUSP | Approved | Approved |
08/17/2022 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | Approved |
08/17/2022 | GAS CLEARANCE | TGAUSP | Approved | CODE |
08/17/2022 | PLUMBING - GAS PRESS TEST FNL | TGAUSP | Approved | Approved with valves installed, please send Clearance to SWG for meter set |
08/17/2022 | MECHANICAL - PROGRESS | TGAUSP | Approved | Approved |
08/17/2022 | PLUMBING - PROGRESS | TGAUSP | Approved | Approved |
08/17/2022 | BUILDING - PROGRESS | TGAUSP | Approved | Approved |
08/17/2022 | U VALUE FOR WINDOW | TGAUSP | Approved | Approved |
08/17/2022 | STUCCO MESH | TGAUSP | Approved | NA |
08/22/2022 | ELECTRIC - FINAL | SCARRAZCO | Approved | approved |
08/23/2022 | PLUMBING - SEWER HCS CONNECT | TGAUSP | Approved | Approved, 4" sanitary and grease line to existing 8" private sewer |
08/24/2022 | PLUMBING - MD GAS/PRECONST MTG | TGAUSP | Approved | NA |
08/25/2022 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
08/25/2022 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
08/26/2022 | BUILDING ABOVE CEILING | TGAUSP | Approved | Approved |
09/06/2022 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
09/08/2022 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
09/09/2022 | FIRE - FINAL | CGates | Approved | The kitchen hood was approved on 9/1/22 T22FC00161. |
09/09/2022 | FIRE - KITCHEN EXH HOOD FINAL | CGates | Approved | Was approved on 9/1/22 T22FC00161 |
09/12/2022 | BUILDING - FINAL | TLUNDBERG | Approved | AP |
09/21/2022 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | Approved |
09/21/2022 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | . Approved. Lighting on building only; no parking lot lighting. |