Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 05/06/2022 |
BUILDING PRE-SLAB |
|
Approved |
Approved, okay for concrete placement |
| 04/13/2022 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial for the area 10’ x 180’ along the entire south wall, and the loading dock receiving area, and the electrical room at the northeast corner (4/12/22) |
| 04/12/2022 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial for the area 10’ x 180’ along the entire south wall, and the loading dock receiving area, and the electrical room at the northeast corner |
| 02/24/2022 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial at Gridlines 1-3 and A-B at east end of building |
| 02/23/2022 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial at Gridline 4/A-G, north end of building |
| 02/02/2022 |
BUILDING PRE-SLAB |
|
Partial Approval |
Partial, under freezer sub slab ok for concrete placement. |