Permit: T21CM06128
Permit Details
Apply Date:
07/28/2021
Applicant:
CHRIS HODGSON
Description:
New metal building shell, covered patios, and interior restaurant fit out. Scope includes Architect
Permit Reviews
Permit Number - T21CM06128
Permit Status: In review
Permit Description: New metal building shell, covered patios, and interior restaurant fit out. Scope includes Architect
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/28/2021 | 3RD PARTY REVIEW - COMMERCIAL | 09/20/2021 | COMPLETED |
09/20/2021 | RESUBMITTAL | 09/30/2021 | COMPLETED |
03/28/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/04/2023 | APPROVED |
08/18/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/22/2023 | APPROVED |
07/21/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/24/2023 | APPROVED |
10/06/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/10/2023 | REQUIRES RESUBMIT |
08/23/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/28/2023 | APPROVED |
01/20/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/08/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM06128
Permit Status: In review
Permit Description: New metal building shell, covered patios, and interior restaurant fit out. Scope includes Architect
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/02/2023 | A final elevation certificate is required before final inspection |
Conditions
Permit Number - T21CM06128
Permit Status: In review
Permit Description: New metal building shell, covered patios, and interior restaurant fit out. Scope includes Architect
Date | Description | Comments |
---|---|---|
09/24/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
09/24/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
09/24/2021 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
09/24/2021 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
09/24/2021 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
09/24/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
09/24/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
09/29/2021 | SPECIAL INSPECTION IS REQ'D FOR AN ELEVATION CERTIFICATE.THE ELEVATION OF THE FORMED PRE-SLAB MUST BE SUBMITTED ON AN ELEVATION CERTIFICATE AND SEALED BY A REGISTERED LAND SURVEYOR. FAX OR EMAIL ELEVATION CERTIFICATE TO: ATTENTION LOREN MAKUS. FAX: 879-8010, EMAIL: LOREN.MAKUS@TUCSONAZ.GOV. THIS CONDITION APPLIES TO INSPECTION 1015 AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. | |
09/29/2021 | FINAL ELEVATION CERTIFICATE REQUIRED: AN ORIGINAL FINAL ELEVATION CERTIFICATE SEALED BY A REGISTERED LAND SURVEYOR IS REQ'D. MAIL ELEVATION CERTIFICATE TO: CITY OF TUCSON, PLANNING & DEVELOPMENT SERVICES DEPT, ATTN: LOREN MAKUS, P.O. BOX 27210, TUCSON, AZ 85726-7210 OR DELIVER IT TO THE 1ST FL NORTH SIDE OF 201 N. STONE AVE. THIS CONDITION APPLIES TO ALL FINAL INSPECTIONS (1090, 2090, 3090, 4090) AND SHOULD NOT BE SCHEDULED UNTIL THE ELEVATION CERTIFICATE AND THE CONDITION HAVE BEEN APPROVED. LOREN'S IS 837-4927. | |
09/24/2021 | SHOP DRAWINGS REQUIRED FOR PREFABRICATE METAL BUILDING | |
09/24/2021 | SHOP DRAWINGS REQUIRED FOR STEEL TRUSSES | |
09/24/2021 | SPECIAL INSPECTION IS REQUIRED FOR STRUCTURAL STEEL. | |
09/29/2021 | FUP T21OT00712 MUST BE PAID BEFORE FINAL INSPECTIONS. | |
09/29/2021 | FUP T21OT00712 MUST BE PAID BEFORE FINAL INSPECTIONS. |
Outstanding Inspections
Permit Status: In Review
Permit Number: T21CM06128
Permite Description: New metal building shell, covered patios, and interior restaurant fit out. Scope includes Architect
Total Outstanding Inspections - 14
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCME - Kitchen Hood | N/A | Not Ready | |
01/04/2023 | COT - LCBU - Building Progress | N/A | Partial Pass | Pre-C of O walk through inspection. |
10/26/2022 | COT - LCBU - Stem Wall/Retaining Wall | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Rough Soil | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
03/07/2023 | COT - LCEL - Electrical Underground | N/A | Partial Pass | 3/7/23. Light pole base furthest west okay to pour concrete 20' of coil copper line with rebar per plan |
10/26/2022 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
03/28/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Partial Pass | UG Plumbing |
07/27/2023 | COT - FCON - Alarm - Final | N/A | Partial Pass | Need to add a horn/strobe in outside bar. |
07/27/2023 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | North and east patio 5-6 heads are blocked by electrical conduit or lighting fixtures, Roll up door on north side of restaurant no coverage under door when open, bag covering head above bar. |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
08/21/2023 | ENGR Engineering Final | N/A | Partial Pass |
Completed Inspections
Permit Status: In Review
Permit Number: T21CM06128
Permit Description: New metal building shell, covered patios, and interior restaurant fit out. Scope includes Architect
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/12/2021 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 11/12/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ufers are in place} | |
11/29/2021 | COT - LCPL - Sewer | Passed | {Activity date: 11/29/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to cover progress areas.} | |
12/01/2021 | COT - LCPL - Yard Water Line | Passed | {Activity date: 12/01/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved. Domestic water line (PVC 1 1/4” line). Ok to cover progress areas.} | |
04/13/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 04/13/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
04/13/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 04/13/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to insulate and cover walls.} | |
10/05/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/05/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to tape throughout. } |
|
11/21/2022 | COT - LCEL - Electrical Above Ceiling | Passed | Canned lighting system in kitchen and food prep areas | |
03/08/2023 | COT - LCPL - Plumbing Progress | Passed | Gas piping. | |
03/30/2023 | BULD - Electrical Clearance | Passed | Approved 1000A service, ECO Clearance to TEP is required | |
04/28/2023 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
04/28/2023 | COT - LCPL - Rough Soil | Passed | ||
04/28/2023 | COT - LCME - Mechanical Final | Passed | ||
04/28/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
04/28/2023 | COT - LCBU - Framing | Passed | ||
04/28/2023 | COT - LCEL - Electrical Underground | Passed | ||
04/28/2023 | COT - LCEL - Electrical Progress | Passed | ||
06/29/2023 | COT - LCBU - Roof Nailing | Passed | ||
06/29/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
06/29/2023 | COT - LCBU - Sustainability | Passed | ||
06/29/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
06/29/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
06/29/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
06/29/2023 | COT - LCPL - Medical Gas Preconstruction Mtg | Passed | ||
06/29/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
06/29/2023 | COT - LCBU - Masonry Pregrout | Passed | ||
06/29/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
06/29/2023 | COT - LCBU - Preslab | Passed | ||
06/30/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
06/30/2023 | COT - LCEL - Construction Power | Passed | ||
07/19/2023 | COT - LCME - Mechanical Progress | Passed | ||
07/19/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
07/19/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
07/19/2023 | COT - LCEL - Electrical Final | Passed | ||
07/19/2023 | COT - LCPL - Plumbing Final | Passed | ||
07/27/2023 | COT - FCON - Hood System - Final | Passed | ||
08/15/2023 | COT - FCON - Alarm - Final | Passed | ||
08/15/2023 | COT - FCON - Sprinkler - Final | Passed | ||
08/21/2023 | COT - HCBU - Building Final | Passed | Passed pending Fire and engineer finals | |
08/23/2023 | ENGR Engineering Final | Passed | GOOD FOR C.O |