Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
Permit Number - T21CM06128
Inspection Description - COT - LCBU - Excavation/Rebar/Zoning
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | Not Ready | ||
01/13/2022 | COT - LCBU - Excavation/Rebar/Zoning | JBURGE | Partial Approval | Entered by VVERA1 - Partial. Column footings (3) on North side of building slab. |
12/30/2021 | COT - LCBU - Excavation/Rebar/Zoning | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial 7 each column footings; planter footings on north east and east sides of the building. Ok to place concrete in progress areas. |
12/23/2021 | COT - LCBU - Excavation/Rebar/Zoning | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial: North stem wall footing. Approximately 150 feet. Ok to place concrete in progress areas |
12/08/2021 | COT - LCBU - Excavation/Rebar/Zoning | JBURGE | Partial Approval | Entered by RSALDAT1 - Partial. Exterior canopy column footings around perimeter of building. Ok to place concrete in progress areas. |
11/12/2021 | COT - LCBU - Excavation/Rebar/Zoning | JBURGE | Partial Approval | Entered by ESTEVEN1 - building footing |
04/28/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed |