Permit: T20CM04413
Permit Details
Apply Date:
07/14/2020
Applicant:
Lisa Bowers
Description:
NEW BUILDING - TCO TO OCCUPY
Permit Reviews
Permit Number - T20CM04413
Permit Status: Expired
Permit Description: NEW BUILDING - TCO TO OCCUPY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/05/2021 | RESUBMITTAL | 02/16/2021 | COMPLETED |
07/14/2020 | COMMERCIAL - NEW | 10/20/2020 | COMPLETED |
10/20/2020 | 3RD PARTY REVIEW - COMMERCIAL | 02/05/2021 | COMPLETED |
10/28/2021 | REVISION - - 1ST | 10/28/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04413
Permit Status: Expired
Permit Description: NEW BUILDING - TCO TO OCCUPY
Total Outstanding Activity Conditions - 9
Date | Name |
---|---|
02/05/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
02/05/2021 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
02/05/2021 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
02/05/2021 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
02/05/2021 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
02/05/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
02/05/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
02/05/2021 | SPECIAL INSPECTION IS REQUIRED FOR STRUCTURAL STEEL |
07/14/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM04413
Permite Description: NEW BUILDING - TCO TO OCCUPY
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/14/2021 | COT - LCEL - Temporary Service | N/A | Canceled | {Activity date: 09/14/2021; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Not Applicable. } |
11/07/2022 | ENGR Engineering Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM04413
Permit Description: NEW BUILDING - TCO TO OCCUPY
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/14/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 04/14/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - CODE ECO/BUILDING 46-MSGD} ; {Activity date: 03/31/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - CODE ECO} | |
09/14/2021 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 07/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - PARTIAL, Data hall above ceiling in Operations Building ok to close ceiling tiles. Fire Putty installed on boxes for office building elevator shaft.} ; {Activity date: 06/29/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection for following equipment complete. (FDC1, FDC2, FDC3).} ; {Activity date: 06/24/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, inspection for following panels complete. (CTC4A, CTC4B). Room 211.} ; {Activity date: 06/14/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection for terminations at following equipment complete. ( MDPU-1A, MDPU-1B, MDPU-2A, MDPU-2B, MDPU-3A, MDPU-3B, MDPU-4A, MDPU-4B, DSA, DSB, CTC-1, CLAN-1). } ; {Activity date: 06/10/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL DATA HALL CONNECTIONS} ; {Activity date: 05/26/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VLEON1 - Partial. North parking lot, conduits for car charging stations ( 4 each at 2 1/2”; 4 at 2”; 2 at 1”); light pole conduits at approximately 200’ with 4 each at 2”. Ok to cover progress areas. } ; {Activity date: 05/25/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Exhaust fans installed on roof and disconnects inspected.} ; {Activity date: 05/24/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Lighting in soffit for connection entrance to OC ok to Sheetrock. Inspection of following equipment completed (Panel LH1, Panel RP-1A, Panel RP-3A, Panel LH1B, Panel RP1B, Panel RP-3B, Panel CLD, Panel CPHB1, Panel CPHB2, & Integrated Switchboard CLHA) ok to energize and lockout tag out circuits. } ; {Activity date: 05/18/2021; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - Partial approval for PDU breaker connections 1B-4B} ; {Activity date: 05/17/2021; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by VLEON1 - } ; {Activity date: 05/14/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection for following equipment for (Air Handler disconnects for 5A, 5B). UPS rooms (1A, 2A, 3A, 4A, 1B, 2B, 3B, 4B, CMDPB)} ; {Activity date: 05/13/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL, Operation Building Electrical in walls complete for following rooms (5146, 5147, 5148, 5150, 5100, 5108, 5109, 5110, 5112, 5113, 5114, 5127A, 5136, 5134, 5130, 5227, 5216, 5226).} ; {Activity date: 05/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection for following equipment complete. 1st floor transformers ( RP3A, PHA, RP1A, RP1B, PHB, PR3B) second floor transformers and panel (RP2A, RP2B, LH2).} ; {Activity date: 04/22/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL, Installation and Inspection for following Electrical equipment complete. (Panel CHPA1, Panel CHPA2, AHU-2A, AHU-2B, CPU-A, CPU-B, CPU-C, CMDPA) Electrical in walls and ceiling Installed for Rooms (105, 106, 107).} ; {Activity date: 04/14/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VLEON1 - PARTIAL ALL TRANS AND SWITCH GEAR OK} ; {Activity date: 04/13/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VLEON1 - PARTIAL - Details from these inspections will be entered on 4/14, once I receive email detailing components and locations of these inspections from contractor.} ; {Activity date: 04/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection of installation and conductor terminations for following equipment approved. (MSG-B Gear sections 2-9, MSG-G, Transformer MOVA, Panel MOVA, Chiller 1, Chiller 2, Chiller 3, Chiller pumps and VFD’s for 1-6, AHU-6A, AHU-6B, AHU-4A, AHU-4B, AHU-3, DP-A1, DP-B1, LDP-1, Generator, T- GPPA, Quick connect for generator & Disconnect for roll up chiller). } ; {Activity date: 04/06/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, no inspection today today see previous notes.} ; {Activity date: 03/31/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Feeders and Overcurrent from MSG-A to (MDS-A, MDS-B, MDS-AB) Inspected and ok to energize these service locations. B side and branch circuit terminations complete but to remain locked and tagged till further inspection.} ; {Activity date: 03/19/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL, Operation center transmission control cable tray installed. Branch circuits installed below 2nd floor from Gl 12-17.} ; {Activity date: 03/10/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Lobby 100 Electrical in south wall ok to sheetrock. Storage room 111 in wall Electrical ok to sheetrock. } |
|
09/14/2021 | COT - LCBU - Framing | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 04/27/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL INSPECTION OF ROOMS 105, 106, 107 OK TO START SHEETROCK} | |
09/14/2021 | COT - LCEL - Electrical Underground | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 04/26/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL SEE PREVIOUS NOTES} ; {Activity date: 03/19/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Low voltage conduits interconnected from OC to exterior vault.} | |
09/14/2021 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 07/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - PARTIAL, inspection for future Training Building Sanitary sewer and water line installed and tested, ok to BACK FILL.} | |
09/14/2021 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 05/26/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VLEON1 - Partial. Operation Center; 72 each VAB Units per plan. Ok to energize systems.} | |
09/14/2021 | COT - LCEL - Construction Power | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 03/31/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Inspection for (MSG-A) ok to Energize Gear on A side only, clear TEP ECO. } |
|
09/14/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 04/22/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL, Inspection for rooms 105, 106, 107(mens, womens and janitor closet) potable water lines and DWV installed and tested.} ; {Activity date: 04/13/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VLEON1 - PARTIAL - Details from these inspections will be entered on 4/14, once I receive email detailing components and locations of these inspections from contractor.} ; {Activity date: 04/07/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, chilled lines under test on data hall 131, MPOP WEST 150,151, MPOP EAST 103,104, UPS room 147 3A. Ok to insulate lines.} ; {Activity date: 04/06/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, no inspection today today see previous notes.} ; {Activity date: 03/19/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL, Chilled main lines installed and under air test for 1st floor. IDF 221 chilled lines installed below 2nd floor.} | |
09/14/2021 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} | |
09/14/2021 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 05/14/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Hydrostatic test on chilled lines complete. } ; {Activity date: 04/22/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL, Hydroponic piping installed and tested at following units ( CRAH-3B, CRAH-1A, CRAH-1B, FCU-1A, FCU-1B, AHU-1A, AHU-1B) } ; {Activity date: 04/21/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, 1st and 2nd floor Low/Medium pressure ducts installed and ok to start insulation. OB} ; {Activity date: 03/19/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL, Chilled main lines installed and under air test for 1st floor & ok to insulate lines. IDF 221 chilled lines installed below 2nd floor. AHU’s installed GL 12-17 below second floor.} |
|
09/14/2021 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} | |
09/14/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 05/05/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, first floor Rooms 105,106,107 ok to tape and proceed. } ; {Activity date: 04/27/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL SEE PREVIOUS NOTES} ; {Activity date: 03/10/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Operating center sheetrock progress.} |
|
09/24/2021 | COT - LCME - Mechanical Final | Passed | {Activity date: 09/24/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved } ; {Activity date: 09/21/2021; Status: Partial Approval; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED} ; {Activity date: 09/15/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Partial, Site inspection for TCO, Provide air balance report prior to final.} ; {Activity date: 09/14/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - ) Not Ready } |
|
09/24/2021 | COT - LCEL - Outdoor Lighting | Passed | {Activity date: 09/24/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved } ; {Activity date: 09/14/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - ) Not Ready } |
|
09/24/2021 | COT - FCON - Sprinkler - Final | Passed | {Activity date: 09/24/2021; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 09/15/2021; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - Trim throughout Leaking riser- level 1 preaction relocate head in chase closet Head leaking in locker room next to 2nd floor dist. center} ; {Activity date: 09/14/2021; Status: Cancelled; Inspector: jfordney; Comment: Entered by JFORDNE1 - } |
|
09/24/2021 | COT - LCPL - Plumbing Final | Passed | {Activity date: 09/24/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved } ; {Activity date: 09/21/2021; Status: Partial Approval; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF WATER DISINFECTION REPORT COMPLETED} ; {Activity date: 09/15/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Partial, Site inspection for TCO, correct ADA required height second floor restroom countertops. Install signage for all restrooms. Provide water chlorination report prior to final. } |
|
12/14/2021 | COT - FCON - Alarm - Final | Passed | {Activity date: 12/14/2021; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 09/17/2021; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - Document box ROC} ; {Activity date: 09/15/2021; Status: Denied; Inspector: jfordney; Comment: Entered by JFORDNE1 - Volume on alarm insufficient smokes where demo to take place need to be retested BDA system Pre-qction switches didn't work} |
|
12/14/2021 | COT - FCON - Fire - Final | Passed | {Activity date: 12/14/2021; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 09/24/2021; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - Approved to obtain TCO} ; {Activity date: 09/23/2021; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - Alarm final approval needed lighting at exit discharges Block access to connector building from south stairwell Data room exit access from terrace NW stairwell egress- no tripping hazard Signage- FDC riser room, FACP electrical rooms} |
|
04/06/2022 | COT - LCBU - Building Final | Passed | {Activity date: 04/06/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/24/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Ok to apply for TCO Operations CENTER only.} ; {Activity date: 09/15/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Partial, site inspection for TCO see notes. Submit all special inspection reports for pending special conditions. Once all conditions have been met walk through is required prior to TCO release.} | |
04/06/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 04/06/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/15/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Partial, Site inspection for TCO, update all panel schedules and install exterior lighting at Egress locations. Seal missed penetrations at fire walls.} ; {Activity date: 09/14/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - ) Not Ready } |