Inspection History Details
Inspection Status: Passed
Inspection History: COT - LCEL - Electrical Intermediate
Permit Number - T20CM04413
Inspection Description - COT - LCEL - Electrical Intermediate
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/14/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Approved | Entered by RSALDAT1 - Approved. |
07/07/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by RSALDAT1 - PARTIAL, Data hall above ceiling in Operations Building ok to close ceiling tiles. Fire Putty installed on boxes for office building elevator shaft. |
06/29/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Inspection for following equipment complete. (FDC1, FDC2, FDC3). |
06/24/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, inspection for following panels complete. (CTC4A, CTC4B). Room 211. |
06/14/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Inspection for terminations at following equipment complete. ( MDPU-1A, MDPU-1B, MDPU-2A, MDPU-2B, MDPU-3A, MDPU-3B, MDPU-4A, MDPU-4B, DSA, DSB, CTC-1, CLAN-1). |
06/10/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - PARTIAL DATA HALL CONNECTIONS |
05/26/2021 | COT - LCEL - Electrical Intermediate | JBURGE | Partial Approval | Entered by VLEON1 - Partial. North parking lot, conduits for car charging stations ( 4 each at 2 1/2”; 4 at 2”; 2 at 1”); light pole conduits at approximately 200’ with 4 each at 2”. Ok to cover progress areas. |
05/25/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Exhaust fans installed on roof and disconnects inspected. |
05/24/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Lighting in soffit for connection entrance to OC ok to Sheetrock. Inspection of following equipment completed (Panel LH1, Panel RP-1A, Panel RP-3A, Panel LH1B, Panel RP1B, Panel RP-3B, Panel CLD, Panel CPHB1, Panel CPHB2, & Integrated Switchboard CLHA) ok to energize and lockout tag out circuits. |
05/18/2021 | COT - LCEL - Electrical Intermediate | WGALLAGHER | Partial Approval | Entered by VLEON1 - Partial approval for PDU breaker connections 1B-4B |
05/17/2021 | COT - LCEL - Electrical Intermediate | DQUINN | Not ready for Inspection | Entered by VLEON1 - |
05/14/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Inspection for following equipment for (Air Handler disconnects for 5A, 5B). UPS rooms (1A, 2A, 3A, 4A, 1B, 2B, 3B, 4B, CMDPB) |
05/13/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - PARTIAL, Operation Building Electrical in walls complete for following rooms (5146, 5147, 5148, 5150, 5100, 5108, 5109, 5110, 5112, 5113, 5114, 5127A, 5136, 5134, 5130, 5227, 5216, 5226). |
05/07/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Inspection for following equipment complete. 1st floor transformers ( RP3A, PHA, RP1A, RP1B, PHB, PR3B) second floor transformers and panel (RP2A, RP2B, LH2). |
04/22/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - PARTIAL, Installation and Inspection for following Electrical equipment complete. (Panel CHPA1, Panel CHPA2, AHU-2A, AHU-2B, CPU-A, CPU-B, CPU-C, CMDPA) Electrical in walls and ceiling Installed for Rooms (105, 106, 107). |
04/14/2021 | COT - LCEL - Electrical Intermediate | DQUINN | Partial Approval | Entered by VLEON1 - PARTIAL ALL TRANS AND SWITCH GEAR OK |
04/13/2021 | COT - LCEL - Electrical Intermediate | DQUINN | Partial Approval | Entered by VLEON1 - PARTIAL - Details from these inspections will be entered on 4/14, once I receive email detailing components and locations of these inspections from contractor. |
04/07/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Inspection of installation and conductor terminations for following equipment approved. (MSG-B Gear sections 2-9, MSG-G, Transformer MOVA, Panel MOVA, Chiller 1, Chiller 2, Chiller 3, Chiller pumps and VFD’s for 1-6, AHU-6A, AHU-6B, AHU-4A, AHU-4B, AHU-3, DP-A1, DP-B1, LDP-1, Generator, T- GPPA, Quick connect for generator & Disconnect for roll up chiller). |
04/06/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, no inspection today today see previous notes. |
03/31/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Feeders and Overcurrent from MSG-A to (MDS-A, MDS-B, MDS-AB) Inspected and ok to energize these service locations. B side and branch circuit terminations complete but to remain locked and tagged till further inspection. |
03/19/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - PARTIAL, Operation center transmission control cable tray installed. Branch circuits installed below 2nd floor from Gl 12-17. |
03/10/2021 | COT - LCEL - Electrical Intermediate | DMUNIZ | Partial Approval | Entered by VLEON1 - Partial, Lobby 100 Electrical in south wall ok to sheetrock. Storage room 111 in wall Electrical ok to sheetrock. |