Inspection Status: Passed
Inspection History: COT - LCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 09/14/2021 |
COT - LCPL - Plumbing Intermediate |
DMUNIZ |
Approved |
Entered by RSALDAT1 - Approved. |
| 04/22/2021 |
COT - LCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - PARTIAL, Inspection for rooms 105, 106, 107(mens, womens and janitor closet) potable water lines and DWV installed and tested. |
| 04/13/2021 |
COT - LCPL - Plumbing Intermediate |
DQUINN |
Partial Approval |
Entered by VLEON1 - PARTIAL - Details from these inspections will be entered on 4/14, once I receive email detailing components and locations of these inspections from contractor. |
| 04/07/2021 |
COT - LCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, chilled lines under test on data hall 131, MPOP WEST 150,151, MPOP EAST 103,104, UPS room 147 3A. Ok to insulate lines. |
| 04/06/2021 |
COT - LCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, no inspection today today see previous notes. |
| 03/19/2021 |
COT - LCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - PARTIAL, Chilled main lines installed and under air test for 1st floor. IDF 221 chilled lines installed below 2nd floor. |