Permit: T20CM02126
Permit Details
Apply Date:
04/07/2020
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW 2-STORY OFFICE BUILDING
Permit Reviews
Permit Number - T20CM02126
Permit Status: C of o
Permit Description: NEW 2-STORY OFFICE BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/04/2021 | REVISION - - 1ST | 03/23/2021 | COMPLETED |
04/07/2020 | PLANS OK TO SUBMIT - COMM | 04/13/2020 | COMPLETED |
04/13/2020 | COMMERCIAL - NEW | 06/23/2020 | COMPLETED |
06/23/2020 | RESUBMITTAL | 08/06/2020 | COMPLETED |
08/06/2020 | RESUBMITTAL | 09/03/2020 | COMPLETED |
12/22/2020 | REVISION - - 1ST | 03/01/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM02126
Permit Status: C of o
Permit Description: NEW 2-STORY OFFICE BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/07/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM02126
Permit Description: NEW 2-STORY OFFICE BUILDING
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/23/2020 | ELECTRIC - UFER | ESTEVENS | Approved | Approved. Attached to rebar. |
09/24/2020 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | Approved. From street connection to property line. |
09/24/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | Partial. Footings and foundation of building only. |
10/08/2020 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | Stem walls at perimeter of building at 16”. Ok to grout progress areas. |
10/08/2020 | STEM WALL/RETAINING WALL | JBURGE | Approved | Shear walls at sidewalk areas at 24”. |
10/21/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | Both are approved. Restrooms, room # 104, 105, 106, 125. |
10/21/2020 | PLUMBING - BACK WATER VALVE | ESTEVENS | Approved | Both are approved. Restrooms, room # 104, 105, 106, 125. |
10/27/2020 | ELECTRIC - UNDERGROUND | JBURGE | Approved | . Partial. Pre-slab Electric conduits interior and exterior. Ok to cover progress areas. |
11/04/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | Approved |
12/11/2020 | FIREWALL/FIREBARRIER/FIRESTOP | ESTEVENS | Approved | Partial. Restroom wall, 104, 106, 06 |
12/11/2020 | FRAMING | ESTEVENS | Approved | Partial. Restroom wall, 104, 106, 06 |
12/11/2020 | ELECTRIC - TEMPORARY SERVICE | ESTEVENS | Approved | Not ready. |
02/05/2021 | ROOF NAILING | JBURGE | Approved | APPROVED THREE PART ROOF SYSTEM, VINYL FINISH LAYER APPLIED |
02/10/2021 | PLUMBING - ROOF DRAINS | DQUINN | Approved | APPROVED |
02/10/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | APPROVED - 2 STORY OSB OK TO MESH |
02/17/2021 | ELECTRIC - PROGRESS | KCOCO | Approved | APPROVED, 2ND FLOOR ONLY |
02/26/2021 | STUCCO MESH | DQUINN | Approved | APPROVED |
04/15/2021 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | |
04/15/2021 | BUILDING - PROGRESS | JBURGE | Approved | Partial. General walk through of building for approximate completion. |
05/28/2021 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
05/28/2021 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | |
06/10/2021 | U VALUE FOR WINDOW | JBURGE | Approved | |
06/10/2021 | BUILDING ABOVE CEILING | JBURGE | Approved | |
08/03/2021 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | Approved |
08/11/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | Approved |
08/11/2021 | ELECTRIC - FINAL | JBURGE | Approved | Approved |
08/11/2021 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | Approved |
08/11/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | Approved |
08/11/2021 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | Approved |
08/11/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Approved |
08/18/2021 | MECHANICAL - FINAL | JBURGE | Approved | Approved. Air balance test results forwarded to Robert Sherry. |
08/24/2021 | PLUMBING - FINAL | JBURGE | Approved | Approved. Results of bacteria test results forwarded to Robert Sherry. |
08/24/2021 | BUILDING - FINAL | JBURGE | Approved | Approved. Pending Fire Finals. Will call for C of O inspection on 25 August. |
08/25/2021 | FIRE - FINAL | CBASALDUA | Approved | |
08/25/2021 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
08/25/2021 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
08/26/2021 | CERTIFICATE OF OCCUPANCY | JBURGE | Approved | 09025. Approved. Ok to make application for Certificate of Occupancy. |
08/26/2021 | ENGINEERING - FINAL | MHERNANDEZ | Approved | APPROVED |
08/30/2021 | ZONING - FINAL | DROBERTS | Approved |