Permit: T20CM02126

Parcel: 117071920


Addresses:

702 S 6TH AV

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
08/11/2021 EXCAVATION/LAYOUT REBAR & ZON Approved Approved
03/12/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Wall footings at utility area (Southwest); North wall footing. Ok to place concrete in progress areas.
09/24/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Footings and foundation of building only.