Permit: T19CM07546
Permit Details
Apply Date:
10/14/2019
Applicant:
N/A
Description:
NEW 63 UNIT MULTI-FAMILY DEVELOPMENT
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T19CM07546
Permit Status: C of o
Permit Description: NEW 63 UNIT MULTI-FAMILY DEVELOPMENT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/17/2020 | RESUBMITTAL | 02/05/2020 | COMPLETED |
03/04/2021 | REVISION - - 1ST | 03/30/2021 | COMPLETED |
05/10/2021 | REVISION - - 2ND | 05/21/2021 | COMPLETED |
10/14/2019 | PLANS OK TO SUBMIT - COMM | 10/17/2019 | COMPLETED |
10/17/2019 | COMMERCIAL - NEW | 11/22/2019 | COMPLETED |
11/27/2019 | RESUBMITTAL - TI ALL | 01/17/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07546
Permit Status: C of o
Permit Description: NEW 63 UNIT MULTI-FAMILY DEVELOPMENT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/14/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM07546
Permit Description: NEW 63 UNIT MULTI-FAMILY DEVELOPMENT
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/28/2020 | ELECTRIC - UFER | ESTEVENS | Approved | Approved |
08/07/2020 | SITE - SEWER | ESTEVENS | Approved | Partial. Northeast corner to northwest corner passed pressure testing. |
08/24/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE TMPP |
08/24/2020 | ELECTRIC - PROGRESS | ESTEVENS | Approved | Partial. Temporary power panel needed to be moved. Inspected new location and approved. Once power is cut the old panel will be removed. The TEP clearance code is TMPP. |
08/27/2020 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | Change to partial status please. From transformer to south side of building to service panels. |
09/09/2020 | PLUMBING - PRE SLAB | ESTEVENS | Approved | Partial. With the gridlines of A1 to A2.5 and H1 to H2.5. |
09/09/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | Partial. With the gridlines of A1 to A2.5 and H1 to H2.5. |
09/16/2020 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | Partial. Yard waterline, from north east corner to stairwell stub out |
09/16/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | Not ready not complete |
10/14/2020 | REINFORCED MASONRY PRE-GROUT | ESTEVENS | Approved | Partial. North east corner to the south east corner site wall. |
10/15/2020 | SHEET ROCK NAILING | ESTEVENS | Approved | Partial. 1st floor ceiling and duct chases on west side of building. |
11/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | Partial. North east corner retaining wall footing. |
11/17/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | Partial. 2nd floor corridor. Gridlines A1 to A3 and AH to H3 |
12/15/2020 | BUILDING - PROGRESS | ESTEVENS | Approved | PARTIAL, NOT READY, NORTH WEST CORNER OF ENTRANCE AND RETAINING WALL. |
12/17/2020 | FRAMING | ESTEVENS | Approved | Partial. Level one. Unit 101, 102, 111, 112. Partial. First floor only, exterior walls that do not contain plumbing, are ok to insulate. |
12/17/2020 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | |
12/17/2020 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
12/17/2020 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | Partial. Level 2. Units 201, 202, 211, 212. Level three units 301, 302, 311, 312. |
12/17/2020 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | Partial. Level one. Unit 101, 102, 111, 112. |
12/29/2020 | ROOF NAILING | ESTEVENS | Approved | Approved. A1 to H1 and A3 to H3. |
12/30/2020 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | APPROVED |
12/30/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | PARTIAL ON UNIT 303, 304, DWV ONLY |
12/30/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | PARTIAL ON UNITS 103, 104, 203, 204 |
12/30/2020 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | PARTIAL ON UNITS 103, 104, 203, 204 |
03/25/2021 | ELECTRIC - FINAL | DQUINN | Approved | |
03/25/2021 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | |
04/02/2021 | TEP CLEARANCE - AM | ESTEVENS | Approved | CODE ECO/UNITS 101-114 |
05/11/2021 | PLUMBING - BACK WATER VALVE | ESTEVENS | Approved | |
05/11/2021 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | |
05/11/2021 | U VALUE FOR WINDOW | ESTEVENS | Approved | |
05/11/2021 | STUCCO MESH | ESTEVENS | Approved | |
06/17/2021 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
06/17/2021 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | |
06/17/2021 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | |
07/15/2021 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | 2036 ,2061, 3035, 3075, 4035, 4075, 4090. All seven are approved. |
07/15/2021 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | 2036 ,2061, 3035, 3075, 4035, 4075, 4090. All seven are approved. |
07/15/2021 | PLUMBING - PROGRESS | ESTEVENS | Approved | 2036 ,2061, 3035, 3075, 4035, 4075, 4090. All seven are approved. |
07/15/2021 | MECHANICAL - PROGRESS | ESTEVENS | Approved | 2036 ,2061, 3035, 3075, 4035, 4075, 4090. All seven are approved. |
07/15/2021 | MECHANICAL - FINAL | ESTEVENS | Approved | 2036 ,2061, 3035, 3075, 4035, 4075, 4090. All seven are approved. |
07/16/2021 | FIRE - FINAL | jfordney | Approved | |
07/16/2021 | FIRE SPKLR - FINAL | jfordney | Approved | |
07/16/2021 | FIRE - ALARM FINAL | jfordney | Approved | |
07/19/2021 | BUILDING - FINAL | RSHERRY | Approved | |
07/19/2021 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |