Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
Permit Number - T19CM07546
Inspection Description - ELECTRIC - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/17/2021 | ELECTRIC - INTERMEDIATE | Approved | ||
04/26/2021 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | ||
04/07/2021 | ELECTRIC - INTERMEDIATE | Cancelled | ||
03/18/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Units 313, 314, 315, 316, 321 and third floor laundry room. | |
03/16/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | PARTIAL UNITS 303 THRU 310 AND ELEVATOR LOBBY | |
03/11/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level #3; Room Units 301; 302; 311; 312 | |
03/11/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Northeast portion of building; SES and switch gear with meter sets for Room Units: 107, 113; 114; 115; 116; 117; 118; 119; 120; 121; 207; 213; 214; 215; 216; 217; 218; 219; 220; 221; 307; 313; 314; 315; 316; 317; 318; 319; 320 321. Ok to energize equipment and set meters. | |
02/16/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level three. Units 313, 314, 315, 316, laundry room, living room, maintenance room. Exterior wall and roof decks are OK to spray foam. | |
02/01/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | PARTIAL EXTERIOR WALLS OF ROOM UNITS 303, 304, 305, 306, 307, 309, 310, 314 OK TO SPRAY INSULATE EXTERIOR WALLS | |
01/29/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level #3; Room Units 301; 302; 311; 312; Electric in walls. Ok to insulate progress areas. | |
01/19/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | PARTIAL ON UNITS #118, #218 | |
01/15/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | PARTIAL LEVEL ONE UNITS 116, 117, 119, 120. LEVEL TWO UNITS 216, 217. | |
01/13/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level 1. Unit 106, 113, 114, 115, 121 and first floor laundry room. Level 2. Units 206, 213, 214, 215, 221, and second floor laundry room. | |
01/11/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. 2nd floor exterior walls are ok to insulate. | |
01/07/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | artial. Unit 105, 107, 108, 205, 207 and 208. Partial. First floor only, exterior walls that do not contain plumbing, are ok to insulate. |
|
01/05/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Units. 110, 109, 209, 210. | |
12/30/2020 | ELECTRIC - INTERMEDIATE | Partial Approval | PARTIAL ON UNITS 103, 104, 203, 204 | |
12/17/2020 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level one. Unit 101, 102, 111, 112. | |
09/01/2020 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | Not ready, not complete. |