Inspection Status: Approved
Inspection History: PLUMBING - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 06/17/2021 |
PLUMBING - ABOVE CEILING |
|
Approved |
|
| 05/12/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Above ceiling in the Corridor‘s in Levels two and three. |
| 05/11/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Level one corridor, laundry room and office. |
| 03/26/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Units 217 through 221. |
| 03/19/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Units. 317, 318, 319, 320. |
| 03/18/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Units 213, 214, 215. |
| 03/04/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Level #2; Room Units 201-212 |
| 03/01/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
PARTIAL - ok in units 201, 202, 212. de in units 203 and 211. Many missed fire caulk locations in these units. |
| 02/24/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Demising walls only, for spray foam insulation. Level three units 315, 316, 317, 318, 319, 320, 321, and level one office bathroom |
| 02/22/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
PARTIAL LEVEL 1 UNITS 117, 118, 119, 120 |
| 02/16/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
PARTIAL FOR UNITS 116, 119, 120 |
| 02/04/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
PARTIAL UNIT #113,114,115, 121 |
| 02/01/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
PARTIAL ROOM UNIT 113 |
| 01/29/2021 |
PLUMBING - ABOVE CEILING |
|
Not ready for Inspection |
NOT READY CANCELLED BY CONTRACTOR |
| 01/27/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Level #1; Room Units 105; 106; 107; 108. |
| 01/22/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Level #1; Room Units 103; 104; 110. Ok to cover progress areas. |
| 01/19/2021 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
PARTIAL ON UNITS 101, 102, 103, 111,112 |
| 12/17/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Level one. Unit 101, 102, 111, 112. |
| 12/17/2020 |
PLUMBING - ABOVE CEILING |
|
Partial Approval |
Partial. Level 2. Units 201, 202, 211, 212. Level three units 301, 302, 311, 312. |