Permit: T19CM06384
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
10150 E GOLF LINKS RD
Address NEW:
10150 E GOLF LINKS RD
Apply Date:
09/03/2019
Applicant:
SEAN DEMARS
Description:
SCHOOL
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T19CM06384
Permit Status: C of o
Permit Description: SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/10/2020 | REVISION - - 1ST | 07/10/2020 | ACTIVE |
| 09/03/2019 | PLANS OK TO SUBMIT - COMM | 09/12/2019 | COMPLETED |
| 09/12/2019 | COMMERCIAL - NEW | 10/10/2019 | COMPLETED |
| 10/21/2019 | RESUBMITTAL | 07/10/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM06384
Permit Status: C of o
Permit Description: SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/03/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM06384
Permit Description: SCHOOL
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/22/2019 | ROOF NAILING | TW | Approved | ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION |
| 11/01/2019 | ELECTRIC - UFER | MRAMBER | Approved | |
| 11/05/2019 | SITE - SEWER | MRAMBER | Approved | |
| 11/05/2019 | PLUMBING - SEWER HCS CONNECT | MRAMBER | Approved | |
| 11/07/2019 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | Interior footers OK |
| 11/14/2019 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
| 11/19/2019 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | Secondary feeders from transformer to SES OK. |
| 11/22/2019 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | Roof drains through foundation up approximately 10 feet OK. |
| 11/25/2019 | BUILDING PRE-SLAB | MRAMBER | Approved | |
| 11/27/2019 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | |
| 12/02/2019 | BUILDING - PROGRESS | MRAMBER | Approved | First lift of cmu ok |
| 12/13/2019 | BUILDING - FINAL | MRAMBER | Approved | Canceled my contractor |
| 12/20/2019 | STEM WALL/RETAINING WALL | MRAMBER | Approved | All top out OK, still need rake at stairwells. |
| 03/03/2020 | TEP CLEARANCE - PM | WGALLAGHER | Approved | CODE ECO |
| 03/03/2020 | ELECTRIC - SERVICE UPGRADE | WGALLAGHER | Approved | Approved for SES connect ok to energize panels 1a, 1b, 1m, 2m, 2ma, 2b, 2a Ok for clearance ECO panel main breakers to no locked out and tag out at this time |
| 03/23/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Electrical in walls ok |
| 06/05/2020 | MECHANICAL - ABOVE CEILING | WGALLAGHER | Approved | |
| 06/05/2020 | PLUMBING - ABOVE CEILING | WGALLAGHER | Approved | |
| 06/05/2020 | ELECTRIC - ABOVE CEILING | WGALLAGHER | Approved | |
| 06/08/2020 | FIRE INTERMEDIATE | MRoss | Approved | Met with superintendent to verify location of access gate on the north side in front of the FDC and on the south side near the fire hydrant. |
| 06/09/2020 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | |
| 06/09/2020 | FRAMING | WGALLAGHER | Approved | |
| 06/09/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | |
| 06/11/2020 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | |
| 06/11/2020 | PLUMBING - PRE SLAB | WGALLAGHER | Approved | |
| 06/11/2020 | ELECTRIC - TEMPORARY SERVICE | WGALLAGHER | Approved | Not a required inspection |
| 06/11/2020 | BUILDING ABOVE CEILING | WGALLAGHER | Approved | |
| 06/18/2020 | U VALUE FOR WINDOW | WGALLAGHER | Approved | |
| 06/30/2020 | MECHANICAL - PROGRESS | WGALLAGHER | Approved | Approved |
| 06/30/2020 | PLUMBING - PROGRESS | WGALLAGHER | Approved | Approved |
| 07/06/2020 | MECHANICAL - FINAL | WGALLAGHER | Approved | Approved |
| 07/09/2020 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved | |
| 07/09/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | Approved |
| 07/09/2020 | ELECTRIC - FINAL | WGALLAGHER | Approved | Approved |
| 07/13/2020 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved |
| 07/13/2020 | RIGHT OF WAY - FINAL | A.Gomez | Approved | Couple of sidewalk panels were damage in front of building. These sidewalk panels were replaced, no issues. |
| 07/23/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | Approved |
| 08/19/2020 | FIRE - FINAL | MRoss | Approved | |
| 08/26/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved |