Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Apply Date:
05/03/2019
Applicant:
N/A
Description:
EXPANSION AND TI: BAR
Architects:
  • CATALANO, VINCENT VICTOR
Contractors:
  • PATE CONTRACTORS LLC

Permit Reviews

Permit Number - T19CM03164
Permit Status: C of o
Permit Description: EXPANSION AND TI: BAR
Start Date Submittal Complete Date Status  
01/17/2020 RESUBMITTAL 02/11/2020 COMPLETED Review Details
02/11/2020 RESUBMITTAL 04/17/2020 COMPLETED Review Details
04/17/2020 REVISION - - 1ST 05/01/2020 COMPLETED Review Details
05/03/2019 COMMERCIAL - TI 05/10/2019 COMPLETED Review Details
05/10/2019 COMMERCIAL - TI 08/23/2019 COMPLETED Review Details
12/13/2019 RESUBMITTAL 01/17/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM03164
Permit Status: C of o
Permit Description: EXPANSION AND TI: BAR
Total Outstanding Activity Conditions - 1
Date Name
05/03/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM03164
Permit Description: EXPANSION AND TI: BAR
Total Completed Inspections - 36
Date Description Inspector Results Comments
04/17/2020 EXCAVATION/LAYOUT REBAR & ZON WGALLAGHER Approved Not ready canceled
04/20/2020 ELECTRIC - UNDERGROUND DMUNIZ Approved RVI Approved, 2- 2 1/2” Conduits from location of new service to interior panels ok to backfill.
04/20/2020 ELECTRIC - UFER DMUNIZ Approved RVI
05/05/2020 ROOF NAILING TTREMBULAK Approved RVI
05/05/2020 EXT METAL CLIPS/EXT SHEATHING TTREMBULAK Approved RVI
05/21/2020 FRAMING TTREMBULAK Approved
06/03/2020 TEP CLEARANCE - PM DMUNIZ Approved CODE INCR
06/03/2020 PLUMBING - INTERMEDIATE DMUNIZ Approved Approved, Grease trap inspected and ok to backfill.
06/03/2020 PLUMBING - ROUGH, SOIL DMUNIZ Approved Approved, Grease trap inspected and ok to backfill.
06/03/2020 ELECTRIC - SERVICE UPGRADE DMUNIZ Approved Clear TEP INCR.
06/22/2020 MECHANICAL - INTERMEDIATE TTREMBULAK Approved Approved
06/22/2020 SITE - SEWER TTREMBULAK Approved Approved
06/22/2020 ELECTRIC - INTERMEDIATE TTREMBULAK Approved Approved
06/23/2020 BUILDING PRE-SLAB WGALLAGHER Approved Approved
06/23/2020 STEM WALL/RETAINING WALL WGALLGHER Approved Not a required inspection
06/23/2020 REINFORCED MASONRY PRE-GROUT WGALLAGHER Approved Not a required inspection
06/24/2020 SHEET ROCK NAILING WGALLAGHER Approved Approved
09/17/2020 FIRE SPKLR - UG PIPING FLUSH wmotto Approved
09/17/2020 FIRE SPKLR - UG, PIPING, HYDRO wmotto Approved
10/02/2020 ENGINEERING - FINAL DROBERTS Approved APPROVED
10/02/2020 ELECTRIC - FINAL TTREMBULAK Approved Partial. Phase one offices, hallway, bar area, and breaker panel.
10/06/2020 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER DISINFECTION REPORT COMPLETED
10/19/2020 CERTIFICATE OF OCCUPANCY TTREMBULAK Approved Partial, phase one office, hallway, bathroom, and bar areas; pending fire and health inspections.
10/19/2020 BUILDING - FINAL TTREMBULAK Approved Partial, phase one office, hallway, bathroom, and bar areas; pending fire and health inspections.
10/20/2020 FIRE SPKLR - FINAL wmotto Approved Partial approval for the south end of the address plus the offices.
1. Still need the north end completed along with the kitchen.
2. Tested tamper and water flow and walked all sprinkler heads within the south end of the address and offices.
2. Fire alarm passed and approved.
3. Need knox box installed on the riser room door.
4. Need the riser room to be labled.
5. Need a sign showing FACP on the Fire alarm door.
6. The Fire alarm has been tested and approved.
10/20/2020 FIRE - FINAL wmotto Approved Partial approval for the south end of the address plus the offices.

1. Still need the north end completed along with the kitchen.
2. Tested tamper and water flow and walked all sprinkler heads within the south end of the address and offices.
2. Fire alarm passed and approved.
3. Need knox box installed on the riser room door.
4. Need the riser room to be labled.
5. Need a sign showing FACP on the Fire alarm door.
6. The Fire alarm has been tested and approved.
7. Need to have keyed lock and thumb turn lock removed from the southwest exit door.
8. Need to have exterior lighing over the exits.

Ok for TCO per Tucson Fire.
11/03/2020 GAS CLEARANCE TTREMBULAK Approved CODE
11/03/2020 PLUMBING - GAS PRESSURE TEST TTREMBULAK Approved Clearance for SWGAS connect ok.
11/13/2020 BUILDING - PROGRESS TTREMBULAK Approved Partial. Interior non-bearing walls; storage,kids, and meeting rooms; ok for drywall.
12/03/2020 MECHANICAL - HOODS TTREMBULAK Approved Partial. Smoke test and insulation wrapping.. ok for final install on plenum.
12/08/2020 ELECTRIC - ABOVE CEILING TTREMBULAK Approved Approved, phase two.
12/08/2020 BUILDING ABOVE CEILING TTREMBULAK Approved Approved, phase two.
02/09/2021 FIRE - KITCHEN EXH HOOD FINAL wmotto Approved
02/10/2021 FIREWALL/FIREBARRIER/FIRESTOP WGALLAGHER Approved NOT APPLICABLE
02/25/2021 MECHANICAL - FINAL TTREMBULAK Approved APPROVED
03/03/2021 HEALTH DEPT - FINAL 724-7908 ARUIZ Approved

Documents

File Name Document Type  
T19CM03164 PLANS CONSTRPLANS VIEW
COFO.PDF CERT OF OCC VIEW
HEALTH DEPARTMENT APPROVED REVIEW.PDF DOCUMENTS VIEW
HEALTH DEPARTMENT FINAL INSPECTION.PDF DOCUMENTS VIEW
SPECIAL INSPECTIONS CERTIFICATE.PDF DOCUMENTS VIEW
TEMPORARY C OF O APPLICATION.PDF DOCUMENTS VIEW
TEMPORARY COFO.PDF DOCUMENTS VIEW
T19CM03164 WATER REPORT.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
1_WOOD TRUSS DRAWINGS & CALCULATIONS.PDF DOCUMENTS VIEW
REV-1_ELECTRICAL PLANS.PDF CONSTRPLANS VIEW
LETTER HEAD.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW