Apply Date:
04/16/2019
Applicant:
RANDEL JACOB
Description:
E - SFR VINO199518 T18-M0082
Architects:
- RANDEL JACOB
Permit Reviews
Permit Number - T19CM02736
Permit Status: Final
Permit Description: E - SFR VINO199518 T18-M0082
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/16/2019 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 05/08/2019 | COMPLETED |
| 05/08/2019 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 05/22/2019 | COMPLETED |
| 05/22/2019 | RESUBMITTAL | 05/24/2019 | COMPLETED |
| 05/24/2019 | RESUBMITTAL | 08/10/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02736
Permit Status: Final
Permit Description: E - SFR VINO199518 T18-M0082
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/16/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM02736
Permit Description: E - SFR VINO199518 T18-M0082
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/06/2020 | PLUMBING - FINAL | GKOZIOL | Approved | No Final and No Certificate of Occupancy until the City of Tucson reviews and approves the location of the private sewer connection for 1105 S 7th Avenue.The private sewer line is crossing the adjacent lot at 1102 S Russell.(same owner). Robert Klepinger is working on drawing revisions and a Private Sewer Joint Use Maintenance Agreement. He wants to get his building permit and start construction as soon as possible.He would like to share the existing 4 HCS recently installed for 1102 S Russell Avenue.The Site Utility Sewer Drawings and the Private Sewer Joint Use Maintenance Agreement need to be reviewed and approved by the City of Tucson, prior to recording and prior to the release of the Final and the Certificate of Occupancy. |
| 08/20/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | Approved |
| 08/20/2020 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved |
| 08/20/2020 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Not Ready |
| 09/04/2020 | ELECTRIC - UFER | JBURGE | Approved | . Approved. |
| 09/04/2020 | BUILDING PRE-SLAB | JBURGE | Approved | Approved. Ok to place concrete in slab areas |
| 10/14/2020 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | Approved. Ok to cover exterior walls on house and garage. |
| 10/14/2020 | ROOF NAILING | JBURGE | Approved | Approved. Ok to dry in roof systems. |
| 10/14/2020 | FRAMING | JBURGE | Approved | Approved. |
| 11/06/2020 | TEP CLEARANCE - PM | JBURGE | Approved | CODE TMPP |
| 11/06/2020 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | . Approved. Clearance; Code: TMPP. Ok to energize for construction power. |
| 11/06/2020 | ELECTRIC - UNDERGROUND | JBURGE | Approved | Approved. Ok to cover progress areas |
| 11/06/2020 | RESIDENTIAL INTERMEDIATE | JBURGE | Approved | Approved. Ok to insulate and cover walls. |
| 11/20/2020 | SHEET ROCK NAILING | JBURGE | Approved | |
| 02/11/2021 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | Approved. Ok to set gas meter. Called in to SW Gas at 1115 hours |
| 03/08/2021 | GAS CLEARANCE | JBURGE | Approved | CODE |
| 03/08/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
| 03/08/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
| 03/08/2021 | MECHANICAL - FINAL | JBURGE | Approved | |
| 03/08/2021 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | |
| 03/08/2021 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | |
| 03/08/2021 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 03/08/2021 | ELECTRIC - FINAL | JBURGE | Approved | |
| 03/08/2021 | BUILDING - FINAL | JBURGE | Approved | |
| 03/08/2021 | STEM WALL/RETAINING WALL | JBURGE | Approved |