Permit: T19CM00826
Permit Details
Apply Date:
02/04/2019
Applicant:
T L W CONSTRUCTION INC ,
Description:
NEW COMMERCIAL BUILDING
Contractors:
- T L W CONSTRUCTION INC ,
Permit Reviews
Permit Number - T19CM00826
Permit Status: C of o
Permit Description: NEW COMMERCIAL BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/04/2019 | PLANS OK TO SUBMIT - COMM | 02/04/2019 | COMPLETED |
02/04/2019 | COMMERCIAL - NEW | 04/12/2019 | COMPLETED |
04/12/2019 | RESUBMITTAL - TI ALL | 04/30/2019 | COMPLETED |
04/30/2019 | RESUBMITTAL | 08/13/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00826
Permit Status: C of o
Permit Description: NEW COMMERCIAL BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/04/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM00826
Permit Description: NEW COMMERCIAL BUILDING
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/10/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | North east quadrant slab ok to pour |
10/10/2019 | BUILDING PRE-SLAB | DQUINN | Approved | North east quadrant slab ok to pour |
11/13/2019 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | |
11/13/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
11/22/2019 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | Third lift of stairwell grouted without inspection. I observed #4s at 32' OC and double #4s at both sides of South wall adjacent to future lintels above. Second #4 is missing from North side of basement lintel, as specified on plans. Builder will obtain RFI, as he believes this should only go to Lintel. Directed builder to contact Inspection Manager for resolution of covered work. |
12/10/2019 | BUILDING - PROGRESS | RCHANDLER | Approved | Pre-Slab level one. |
12/11/2019 | FRAMING | RCHANDLER | Approved | Shear walls in basement. |
05/01/2020 | U VALUE FOR WINDOW | ESTEVENS | Approved | RVI |
05/21/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
05/21/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | The TEP clearance code is ECO. |
07/27/2020 | ELECTRIC - FINAL | WGALLAGHER | Approved | Approved |
07/28/2020 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | Approved |
07/31/2020 | ELECTRIC - PROGRESS | WGALLAGHER | Approved | SEE 2090 |
07/31/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | SEE 2090 |
07/31/2020 | MECHANICAL - FINAL | WGALLAGHER | Approved | Approved |
07/31/2020 | MECHANICAL - PROGRESS | WGALLAGHER | Approved | Approved |
07/31/2020 | ROOF NAILING | WGALLAGHER | Approved | Approved |
07/31/2020 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | Approved |
07/31/2020 | ELECTRIC - INTERMEDIATE | WGALLAGHER | Approved | Approved |
07/31/2020 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | Approved |
07/31/2020 | ELECTRIC - ABOVE CEILING | WGALLAGHER | Approved | Not a required inspection |
07/31/2020 | MECHANICAL - ABOVE CEILING | WGALLAGHER | Approved | Not a required inspection |
07/31/2020 | STUCCO MESH | WGALLAGHER | Approved | Not a required inspection |
07/31/2020 | ELECTRIC - SERVICE UPGRADE | WGALLAGHER | Approved | Not a required inspection |
08/06/2020 | FIRE SPKLR - FINAL | MRoss | Approved | |
08/06/2020 | LANDSCAPE - FINAL | DROBERTS | Approved | IS APPROVED AT THIS TIME. MINOR REPAIR WORK IS BEING COMPLETED BY THE END OF DAY ON 8/7/20. |
08/07/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | All three are approved. |
08/07/2020 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | All three are approved. |
08/12/2020 | SIGN - FINAL | RLEDONNE | Approved | Approved. |
08/12/2020 | NPPO - FINAL | RLEDONNE | Approved | Approved. |
08/12/2020 | RIGHT OF WAY - FINAL | MVV | Approved | No work in right of way. |
08/18/2020 | FIRE - FINAL | MRoss | Approved | |
08/18/2020 | FIRE - ALARM FINAL | MRoss | Approved | |
08/28/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved. |
08/31/2020 | BUILDING - FINAL | TTREMBULAK | Approved | Approved |