Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 07/31/2020 |
BUILDING - PROGRESS |
|
Approved |
Approved |
| 03/03/2020 |
BUILDING - PROGRESS |
|
Approved |
east deck 2nd floor prepour |
| 02/27/2020 |
BUILDING - PROGRESS |
|
Partial Approval |
Preslab West half of level two. |
| 02/25/2020 |
BUILDING - PROGRESS |
|
Partial Approval |
West of elevator 2nd floor deck for concrete. Still needs rebar tie-ins and wire mesh. |
| 12/10/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Pre-Slab level one. |
| 12/06/2019 |
BUILDING - PROGRESS |
|
Correction Required |
West half poured when I arrived. This is the second inspection where work has been covered without approval. Do not proceed until these have been resolved. Super not on job; left voicemail with contact on record directing them to contact Inspection Manager. |