Permit: T19CM00123
Permit Details
Apply Date:
01/08/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
BOWLING ALLEY
Contractors:
- TWIN SHORES MANGEMENT LLC
Permit Reviews
Permit Number - T19CM00123
Permit Status: C of o
Permit Description: BOWLING ALLEY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/08/2019 | PLANS OK TO SUBMIT - COMM | 01/08/2019 | COMPLETED |
01/17/2019 | COMMERCIAL - TI | 03/19/2019 | COMPLETED |
03/19/2019 | RESUBMITTAL | 08/09/2019 | COMPLETED |
08/09/2019 | REVISION - - 1ST | 09/05/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00123
Permit Status: C of o
Permit Description: BOWLING ALLEY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/08/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM00123
Permit Description: BOWLING ALLEY
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/26/2019 | GAS CLEARANCE | DQUINN | Approved | |
07/26/2019 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | CLEAR GAS |
08/14/2019 | FRAMING | RCHANDLER | Approved | |
09/06/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
09/09/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | Via FaceTime |
09/18/2019 | ELECTRIC - SERVICE UPGRADE | MRAMBER | Approved | |
09/18/2019 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | |
09/18/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | No work outside of building per approved plans. |
10/03/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
10/03/2019 | PLUMBING - FINAL | MRAMBER | Approved | Pending sterilization report. |
10/03/2019 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
10/07/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
10/07/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
10/07/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
10/11/2019 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved | |
10/11/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | Pending balance report approval. |
10/11/2019 | CERTIFICATE OF OCCUPANCY | RCHANDLER | Approved | Pending other inspections, balance report approval. |
10/16/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
10/16/2019 | FIRE - ALARM FINAL | MRoss | Approved | |
11/07/2019 | BUILDING - FINAL | RCHANDLER | Approved | FIRE INSPECTION COMPLETED 11/07/19 |
11/07/2019 | FIRE - FINAL | MRoss | Approved |