Permit: T19CM00123

Parcel: 128010040

Inspection Status: Approved

Inspection History: MECHANICAL - INTERMEDIATE

Date Description Inspector Results Comments
09/09/2019 MECHANICAL - INTERMEDIATE Approved Via FaceTime
08/19/2019 MECHANICAL - INTERMEDIATE Partial Approval Waiting on VAV units to be delivered.
All side rooms on 1st and 2nd floor ok for drop grid installation.
08/14/2019 MECHANICAL - INTERMEDIATE Partial Approval Smoke test on second duct and first layer of first duct(from previous inspection).
08/09/2019 MECHANICAL - INTERMEDIATE Partial Approval One grease duct OK smoke test, other grease duct failed smoke test
08/08/2019 MECHANICAL - INTERMEDIATE Not ready for Inspection canceled on-site with builder.