Permit: T19CM00016
Permit Details
Apply Date:
01/02/2019
Applicant:
WILSON ELECTRIC SERVICES CORP ** APA **
Description:
Commercial solar, Sierra Middle School, INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT
Contractors:
- WILSON ELECTRIC SERVICES CORP ** APA **
Permit Reviews
Permit Number - T19CM00016
Permit Status: Final
Permit Description: Commercial solar, Sierra Middle School, INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/02/2019 | WALK THRU - COMM | 01/31/2019 | COMPLETED |
| 03/26/2019 | RESUBMITTAL | 04/03/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00016
Permit Status: Final
Permit Description: Commercial solar, Sierra Middle School, INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/02/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM00016
Permit Description: Commercial solar, Sierra Middle School, INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/04/2019 | ELECTRIC - UFER | RCAMACHO | Approved | |
| 06/04/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | |
| 07/03/2019 | ROOF NAILING | AKLEINSORGE | Approved | Bolting of panels to structural steel for 5 canopies |
| 07/03/2019 | FRAMING | AKLEINSORGE | Approved | Bolting of columns to beams for 5 canopies |
| 07/15/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
| 07/31/2019 | ELECTRIC - OUTDOOR LIGHTING | MHASSAN | Approved | |
| 08/14/2019 | BUILDING - PROGRESS | AKLEINSORGE | Approved | |
| 08/14/2019 | ELECTRIC - INTERMEDIATE | AKLEINSORGE | Approved | |
| 08/17/2019 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Interconnection from 500AMP PV Utility, Disconnect to Existing 2000 AMP 277/480V SES. 2 Parallel sets of 3-#400MCM AL Conductors, 1- #1/0 AL Grnd, in 2-3” RMC Conduits. Sent verbal Clearance To TEP @ 10:50AM (RECN/DGC). Upon arrival collected check for after hours inspection, for $165. |
| 08/17/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | Interconnection from 500AMP PV Utility, Disconnect to Existing 2000 AMP 277/480V SES. 2 Parallel sets of 3-#400MCM AL Conductors, 1- #1/0 AL Grnd, in 2-3” RMC Conduits. Sent verbal Clearance To TEP @ 10:50AM (RECN/DGC). Upon arrival collected check for after hours inspection, for $165. |
| 08/17/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | Interconnection from 500AMP PV Utility, Disconnect to Existing 2000 AMP 277/480V SES. 2 Parallel sets of 3-#400MCM AL Conductors, 1- #1/0 AL Grnd, in 2-3” RMC Conduits. Sent verbal Clearance To TEP @ 10:50AM (RECN/DGC). Upon arrival collected check for after hours inspection, for $165. |
| 08/17/2019 | BUILDING - FINAL | DMUNIZ | Approved | |
| 09/10/2019 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE DGC |