Permit: T18CM07123
Permit Details
Status:
Final
Type:
COMMERCIAL NEW
Address:
6721 S RENAISSANCE DR
Address NEW:
6721 S RENAISSANCE DR
Apply Date:
09/10/2018
Applicant:
JACA DESIGNN LLC - FLOREZ, JESUS L.
Description:
NEW FACTORY: SHELL BUILDING
Architects:
- FLOREZ, JESUS L.
Contractors:
- S AND R CARPENTRY AND BUILDERS LLC
Permit Reviews
Permit Number - T18CM07123
Permit Status: Final
Permit Description: NEW FACTORY: SHELL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/09/2019 | COMMERCIAL - NEW | 05/31/2019 | COMPLETED |
| 05/31/2019 | RESUBMITTAL - TI ALL | 07/10/2019 | COMPLETED |
| 07/26/2019 | RESUBMITTAL - TI ALL | 09/06/2019 | COMPLETED |
| 09/06/2019 | RESUBMITTAL - TI ALL | 09/23/2019 | COMPLETED |
| 09/10/2018 | PLANS OK TO SUBMIT - COMM | 04/09/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07123
Permit Status: Final
Permit Description: NEW FACTORY: SHELL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/10/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM07123
Permit Description: NEW FACTORY: SHELL BUILDING
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/08/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 10/08/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 10/14/2019 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 10/14/2019 | ELECTRIC - UFER | TVALENCIA | Approved | 1- Ufer ground conductor provided. |
| 10/14/2019 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
| 01/10/2020 | PLUMBING - SEWER HCS CONNECT | WGALLAG1 | Approved | |
| 01/10/2020 | FRAMING | WGALLAG1 | Approved | |
| 01/10/2020 | ROOF NAILING | WGALLAG1 | Approved | |
| 01/15/2020 | PLUMBING - BACK WATER VALVE | WGALLAG1 | Approved | |
| 07/22/2020 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE ECO |
| 07/22/2020 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | approved Clear electric ECO |
| 07/22/2020 | ELECTRIC - TEMPORARY SERVICE | TVALENCIA | Approved | approved |
| 11/24/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | |
| 12/14/2020 | PLUMBING - FINAL | DMUNIZ | Approved | APPROVED. |
| 12/14/2020 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | Approved |
| 12/14/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 12/14/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | APPROVED. |
| 12/21/2020 | FIRE - ALARM FINAL | MRoss | Approved | |
| 12/23/2020 | BUILDING - FINAL | DMUNIZ | Approved | INSPECTOR APPROVED BUILDING FINAL. PENDING FIRE INSPECTION. |
| 12/23/2020 | FIRE - FINAL | MRoss | Approved | Exit signs backup power not working at time of inspection |
| 12/23/2020 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 12/28/2020 | ENGINEERING - FINAL | DROBERTSEZ | Approved | IS APPROVED |