Permit: T18CM06111
Permit Details
Apply Date:
08/07/2018
Applicant:
N/A
Description:
RESTAURANT
Contractors:
- FOOD SERVICE CONCEPTS INC
Permit Reviews
Permit Number - T18CM06111
Permit Status: C of o
Permit Description: RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/03/2019 | RESUBMITTAL | 01/03/2019 | COMPLETED |
| 01/03/2019 | OTHER | 04/16/2019 | COMPLETED |
| 08/07/2018 | PLANS OK TO SUBMIT - COMM | 08/15/2018 | COMPLETED |
| 08/15/2018 | COMMERCIAL - NEW | 09/28/2018 | COMPLETED |
| 09/28/2018 | RESUBMITTAL | 11/21/2018 | COMPLETED |
| 11/21/2018 | RESUBMITTAL | 01/03/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM06111
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/07/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM06111
Permit Description: RESTAURANT
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2018 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 12/10/2018 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 05/06/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | ok to backfill |
| 06/05/2019 | PLUMBING - PROGRESS | DMUNIZ | Approved | DWV test on Interior plumbing top out Ok. |
| 06/05/2019 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | ok to backfill. |
| 06/06/2019 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | |
| 06/06/2019 | ROOF NAILING | DMUNIZ | Approved | |
| 06/07/2019 | PLUMBING - BACK WATER VALVE | DMUNIZ | Approved | |
| 06/07/2019 | SITE - SEWER | DMUNIZ | Approved | |
| 06/14/2019 | ELECTRIC - UFER | DMUNIZ | Approved | Uffer for Ext Light poles. |
| 06/26/2019 | SHEET ROCK NAILING | DMUNIZ | Approved | |
| 07/09/2019 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
| 07/09/2019 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | |
| 07/09/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
| 07/09/2019 | FRAMING | DMUNIZ | Approved | |
| 07/09/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
| 07/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
| 07/16/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | HCS & 1200 Gallon Grease Interceptor ok to backfill. |
| 07/17/2019 | GAS CLEARANCE | DMUNIZ | Approved | Clear Southwest Gas. |
| 07/17/2019 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Clear Southwest Gas. |
| 08/07/2019 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
| 08/09/2019 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
| 08/09/2019 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Clear TEP (ECO). 600AMP SES ok to energize. |
| 08/09/2019 | ELECTRIC - TEMPORARY SERVICE | DMUNIZ | Approved | |
| 08/21/2019 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | |
| 08/21/2019 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | |
| 08/21/2019 | U VALUE FOR WINDOW | DMUNIZ | Approved | |
| 08/21/2019 | BUILDING ABOVE CEILING | DMUNIZ | Approved | |
| 08/21/2019 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | |
| 08/21/2019 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | |
| 08/21/2019 | BUILDING - PROGRESS | DMUNIZ | Approved | |
| 08/23/2019 | MECHANICAL - HOODS | DMUNIZ | Approved | smoke test performed on both Hood Vents. |
| 08/26/2019 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved | |
| 08/27/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 08/29/2019 | FIRE - KITCHEN EXH HOOD FINAL | MRoss | Approved | |
| 08/29/2019 | FIRE - ALARM FINAL | MRoss | Approved | |
| 08/29/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 08/29/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 08/29/2019 | BUILDING - FINAL | DMUNIZ | Approved | |
| 09/11/2019 | FIRE - FINAL | MRoss | Approved | Operational permit required for Places of Assembly through the Tucson Fire Department |
| 09/13/2019 | ENGINEERING - FINAL | rledonn1 | Approved | |
| 09/13/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | Pending development package approval. |
| 10/29/2019 | CERTIFICATE OF OCCUPANCY | KROBLES | Approved |