Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
3600 E HEMISPHERE LP
Apply Date:
07/18/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW OFFICE BUILDING
Architects:
  • ACORN, KIM BRIAN
Contractors:
  • CHESTNUT BUILDING & DESIGN INC

Permit Reviews

Permit Number - T18CM05587
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
Start Date Submittal Complete Date Status  
07/18/2018 PLANS OK TO SUBMIT - COMM 07/18/2018 COMPLETED Review Details
07/19/2018 COMMERCIAL - NEW 08/29/2018 COMPLETED Review Details
08/12/2019 REVISION - - 1ST 08/13/2019 ACTIVE Review Details
08/29/2018 RESUBMITTAL 10/02/2018 COMPLETED Review Details
10/02/2018 RESUBMITTAL 10/04/2018 COMPLETED Review Details
10/04/2018 RESUBMITTAL 10/08/2018 COMPLETED Review Details
10/08/2018 RESUBMITTAL 08/12/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM05587
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
Total Outstanding Activity Conditions - 1
Date Name
07/18/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM05587
Permit Description: NEW OFFICE BUILDING
Total Completed Inspections - 44
Date Description Inspector Results Comments
08/01/2018 PLUMBING - FINAL RSHERRY Approved WATER CHLORINATION REPORT REQUIRED
10/03/2018 MECHANICAL - FINAL RSHERRY Approved AIR BALANCE REPORT REQUIRED
11/06/2018 PLUMBING - SEWER HCS CONNECT RCHANDLER Approved
11/14/2018 PLUMBING - ROUGH, SOIL DMCCARTHY Approved Came back later to reinspect. Commercial building, under ground stage.
11/14/2018 PLUMBING - ROUGH, SOIL DMCCARTHY Approved .10 foot riser not holding water. No water in 10 foot rise
11/20/2018 ELECTRIC - UFER DMUNIZ Approved MAIN BUILDING 30K SQ FT. OK TO POUR
11/20/2018 BUILDING PRE-SLAB DMUNIZ Approved MAIN BUILDING 30K SQ FT. OK TO POUR
11/20/2018 STEM WALL/RETAINING WALL DMUNIZ Approved MAIN BUILDING 30K SQ FT. OK TO POUR
11/20/2018 EXCAVATION/LAYOUT REBAR & ZON DMUNIZ Approved MAIN BUILDING 30K SQ FT. OK TO POUR
12/06/2018 PLUMBING - YARD WTR LINE/TEST MHASSAN Approved
12/07/2018 FIRE SPKLR - UG, PIPING, HYDRO gsereno1 Approved
12/20/2018 ELECTRIC - UNDERGROUND DQUINN Approved Last 8 light pole bases and grounding ok to pour
03/05/2019 ROOF NAILING MHASSAN Approved
04/08/2019 FIRE SPKLR - UG PIPING FLUSH Mross Approved
04/10/2019 PLUMBING - ABOVE CEILING AKLEINSORGE Approved
05/13/2019 TEP CLEARANCE - PM AKLEINSORGE Approved CODE ECO
05/13/2019 ELECTRIC - TEMPORARY SERVICE AKLEINSORGE Approved
05/13/2019 ELECTRIC - CONSTRUCTION POWER AKLEINSORGE Approved Clear eco
07/05/2019 MECHANICAL - ABOVE CEILING AKLEINSORGE Approved Training Room, Mail Room, Archive Room, File Room and Work Room
07/05/2019 ELECTRIC - ABOVE CEILING AKLEINSORGE Approved Training Room, Mail Room, Archive Room, File Room and Work Room
07/05/2019 BUILDING ABOVE CEILING AKLEINSORGE Approved Training Room, Mail Room, Archive Room, File Room and Work Room
07/05/2019 FRAMING AKLEINSORGE Approved
07/05/2019 EXT METAL CLIPS/EXT SHEATHING AKLEINSORGE Approved
07/16/2019 STUCCO MESH AKLEINSORGE Approved
07/16/2019 U VALUE FOR WINDOW AKLEINSORGE Approved
07/16/2019 MECHANICAL - INTERMEDIATE AKLEINSORGE Approved All work is complete
07/16/2019 PLUMBING - INTERMEDIATE AKLEINSORGE Approved All work is complete
07/16/2019 PLUMBING - ROOF DRAINS AKLEINSORGE Approved All work is complete
07/16/2019 PLUMBING - PROGRESS AKLEINSORGE Approved All work is complete
07/16/2019 ELECTRIC - INTERMEDIATE AKLEINSORGE Approved All work is complete
07/16/2019 BUILDING - PROGRESS AKLEINSORGE Approved All work is complete
07/16/2019 REINFORCED MASONRY PRE-GROUT AKLEINSORGE Approved All work is complete
07/19/2019 ELECTRIC - FINAL MHASSAN Approved
07/19/2019 OUTDOOR LIGHTING FINAL MHASSAN Approved
07/19/2019 ELECTRIC - OUTDOOR LIGHTING MHASSAN Approved
07/19/2019 ELECTRIC - PROGRESS MHASSAN Approved
07/19/2019 FIREWALL/FIREBARRIER/FIRESTOP MHASSAN Approved
07/19/2019 SITE - SEWER MHASSAN Approved
07/24/2019 FIRE - ALARM FINAL gsereno1 Approved
07/24/2019 FIRE SPKLR - FINAL gsereno1 Approved
08/02/2019 ENGINEERING - FINAL DROBERTS Approved
08/13/2019 CERTIFICATE OF OCCUPANCY MHASSAN Approved CHOLRINATION REPORT APPROVED,FIRE FINAL AND ENGINEERRING FINAL APPROVED
08/13/2019 FIRE - FINAL GSERRANO1 Approved
08/14/2019 BUILDING - FINAL AKLEINSORGE Approved All other approvals are completed