Permit: T18CM05587

Parcel: 14029200A

Inspection Status: Approved

Inspection History: ELECTRIC - UNDERGROUND

Date Description Inspector Results Comments
08/14/2019 ELECTRIC - UNDERGROUND Approved
12/20/2018 ELECTRIC - UNDERGROUND Partial Approval Last 8 light pole bases and grounding ok to pour
12/19/2018 ELECTRIC - UNDERGROUND Partial Approval 7 light pole bases - conduit, rebar, and ufers ok to pour
12/19/2018 ELECTRIC - UNDERGROUND Cancelled IVRS - AP canceled
12/18/2018 ELECTRIC - UNDERGROUND Cancelled IVRS - AP canceled
12/11/2018 ELECTRIC - UNDERGROUND Partial Approval PVC conduit for light pole bases. 3/4" to and from each pole location. No boring or cages installed at this inspection.
3-3" Conduits for secondaries from transformer location to distribution service. Per plan sheet ES101
11/14/2018 ELECTRIC - UNDERGROUND Approved
11/07/2018 ELECTRIC - UNDERGROUND Partial Approval first half of electric room complete
11/07/2018 ELECTRIC - UNDERGROUND Partial Approval Conduit for electric room complete. 14 PVC conduits 3/4" and 1".